Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Dec 2021 | CC 10th and part bill submitted.1987FHTCs given | Chalakudy AEE | |
11 Dec 2021 | Actual completed FHTC Provided till date is 1987numbers. | Chalakudy AE 1 | |
06 Dec 2021 | Actual completed FHTC Provided till date is 1987numbers. | Chalakudy AE 1 | |
03 Dec 2021 | Actual completed FHTC Provided till date is 1987numbers. | Chalakudy AE 1 | |
29 Nov 2021 | Actual completed FHTC Provided till date is 1987numbers. | Chalakudy AE 1 | |
29 Nov 2021 | Actual completed FHTC Provided till date is 1956numbers. | Chalakudy AE 1 | |
22 Nov 2021 | Actual completed FHTC Provided till date is 1956numbers. | Chalakudy AE 1 | |
18 Nov 2021 | Actual completed FHTC Provided till date is 1956numbers. | Chalakudy AE 1 | |
15 Nov 2021 | Actual completed FHTC Provided till date is 1956numbers. | Chalakudy AE 1 | |
11 Nov 2021 | Actual completed FHTC Provided till date is 1956numbers. | Chalakudy AE 1 |