Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Aug 2022 | Final bill submitted to Dn. 1988 FHTCs given totally. | Chalakudy AEE | |
28 Feb 2022 | work completed | Chalakudy AE 1 | |
22 Feb 2022 | work completed | Chalakudy AE 1 | |
01 Feb 2022 | 99% completed | Chalakudy AE 1 | |
12 Jan 2022 | 99% completed | Chalakudy AE 1 | |
12 Jan 2022 | 98% completed | Chalakudy AE 1 | |
04 Jan 2022 | cc 10th part bill Paid 20-12-2021 | Irinjalakkuda PH Dn EE | |
04 Jan 2022 | CC 10th and part bill submitted.1987FHTCs given | Chalakudy AE 1 | |
30 Dec 2021 | CC 10th and part bill submitted.1987FHTCs given | Chalakudy AE 1 | |
28 Dec 2021 | CC 10th and part bill submitted.1987FHTCs given | Chalakudy AE 1 |