Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Feb 2024 53km laying completed out of 166km.1519 connections given out of 7820 connections. Construction work of Tranformer room completed.750kVA transformer supplied. Kottayam AE 3
27 Jul 2022 Meeting at Ayarkunnam panchayath was held on 20.07.2022 panchayath authorities KWA EE,AEE,AE,ISA and JJM staff attended the meating to discuss the progress and issues in on going JJM works. Kottayam AE 3
04 Feb 2022 In Package 1, 9km 90mm PVC Pipe laid out of 61km. Kottayam AE 3
08 Nov 2021 In Package 1, 4km 90mm PVC Pipe laid out of 41km.Pipe laying and connection work progressing in Panchayath roads.PWD road cutting permission pending in 3 reaches. Road restoration amount remitted for 9 reaches. Agreement not executed .Letter given to contractor on 27-10-2021 to supply pipe materials for laying in those PWD roads. Package 2- Sub station room roof slab concreting work completed. Now FHTC work progressing in panchayath roads. In Package 4 ,2.4km pvc pipe laid out of 6 km Kottayam AE 3
07 Nov 2021 4km/41km pipe laid and 493/7820 FHTC given Kottayam AE 3
01 Oct 2021 Meeting conducted at PWD EE's chamber on 30-09-2021 with EE Project Division. AEEs and AEs to discuss the issues related with pending road cutting approvals. Kottayam AE 3
14 Sep 2021 Package 1-0.5km/41km pipeline laid,package 3-3.9km/3.9km pipe laid, package 4-1.5km/6km pipeline laid Kottayam AE 3
03 Sep 2021 EE conducted a meeting with JJM contractors, AEEs and AEs on 1-9-2021 to discuss progress of work Kottayam AE 3
27 Aug 2021 Package 4- 90mm PVC laying and 300mm DI laying progressing Kottayam AE 3
20 Aug 2021 Package I-Pipe not supplied at site,Package II-No work,Package III-Work completed,Package IV-No work Kottayam AE 3