Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Feb 2024 | 53km laying completed out of 166km.1519 connections given out of 7820 connections. Construction work of Tranformer room completed.750kVA transformer supplied. | Kottayam AE 3 | |
27 Jul 2022 | Meeting at Ayarkunnam panchayath was held on 20.07.2022 panchayath authorities KWA EE,AEE,AE,ISA and JJM staff attended the meating to discuss the progress and issues in on going JJM works. | Kottayam AE 3 | |
04 Feb 2022 | In Package 1, 9km 90mm PVC Pipe laid out of 61km. | Kottayam AE 3 | |
08 Nov 2021 | In Package 1, 4km 90mm PVC Pipe laid out of 41km.Pipe laying and connection work progressing in Panchayath roads.PWD road cutting permission pending in 3 reaches. Road restoration amount remitted for 9 reaches. Agreement not executed .Letter given to contractor on 27-10-2021 to supply pipe materials for laying in those PWD roads. Package 2- Sub station room roof slab concreting work completed. Now FHTC work progressing in panchayath roads. In Package 4 ,2.4km pvc pipe laid out of 6 km | Kottayam AE 3 | |
07 Nov 2021 | 4km/41km pipe laid and 493/7820 FHTC given | Kottayam AE 3 | |
01 Oct 2021 | Meeting conducted at PWD EE's chamber on 30-09-2021 with EE Project Division. AEEs and AEs to discuss the issues related with pending road cutting approvals. | Kottayam AE 3 | |
14 Sep 2021 | Package 1-0.5km/41km pipeline laid,package 3-3.9km/3.9km pipe laid, package 4-1.5km/6km pipeline laid | Kottayam AE 3 | |
03 Sep 2021 | EE conducted a meeting with JJM contractors, AEEs and AEs on 1-9-2021 to discuss progress of work | Kottayam AE 3 | |
27 Aug 2021 | Package 4- 90mm PVC laying and 300mm DI laying progressing | Kottayam AE 3 | |
20 Aug 2021 | Package I-Pipe not supplied at site,Package II-No work,Package III-Work completed,Package IV-No work | Kottayam AE 3 |