JJM-WSS to Ayarkunnam Panchayath

Project JJM-WSS to Ayarkunnam Panchayath
Project Code KTMJJM12206034
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Supplying and laying DI/PVC/GI distribution system and providing FHTCs
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
AS Amount (Rs) 367100000
AS Number 777/2020/WRD
TS Amount (Rs) 316490000
TS Number 14727/2020-2021
Total Bill Submitted (Rs) 32312308
Total Bill Paid (Rs) 32312308
Population Benefitted 28718
Capacity in MLD 12.00
Actual Project Completion Date 08 Feb 2022
Coverage Ayarkunnam Panchayath area
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-WSS to Ayarkunnam Panchayath Package 1-Supplying and laying DI/PVC/GI distribution system and providing FHTCs in 2 zones Kottayam Project Dn
2 JJM-WSS to Ayarkunnam Panchayath Package 2 Kottayam Project Dn
3 JJM-WSS to Ayarkunnam Panchayath Package 3 Kottayam Project Dn
4 JJM-WSS to Ayarkunnam Panchayath Package 4 Kottayam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Feb 2024 53km laying completed out of 166km.1519 connections given out of 7820 connections. Construction work of Tranformer room completed.750kVA transformer supplied. Kottayam AE 3
27 Jul 2022 Meeting at Ayarkunnam panchayath was held on 20.07.2022 panchayath authorities KWA EE,AEE,AE,ISA and JJM staff attended the meating to discuss the progress and issues in on going JJM works. Kottayam AE 3
04 Feb 2022 In Package 1, 9km 90mm PVC Pipe laid out of 61km. Kottayam AE 3
08 Nov 2021 In Package 1, 4km 90mm PVC Pipe laid out of 41km.Pipe laying and connection work progressing in Panchayath roads.PWD road cutting permission pending in 3 reaches. Road restoration amount remitted for 9 reaches. Agreement not executed .Letter given to contractor on 27-10-2021 to supply pipe materials for laying in those PWD roads. Package 2- Sub station room roof slab concreting work completed. Now FHTC work progressing in panchayath roads. In Package 4 ,2.4km pvc pipe laid out of 6 km Kottayam AE 3
07 Nov 2021 4km/41km pipe laid and 493/7820 FHTC given Kottayam AE 3

Project Review

See All Review messages
Review Date Review Message Review Attended By
03 Feb 2021 project components ,officers in charge etc to be added

Duration & Sanction dates

Date of start of Project 04/02/2021
Scheduled date of Completion of the Project 06 Feb 2022
Expected date of Completion 25/03/2024

Processing Dates

AS Date 24 Dec 2020
TS Date 16 Jan 2021