Project | JJM-WSS to Ayarkunnam Panchayath |
---|---|
Project Code | KTMJJM12206034 |
Type | Main project |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Supplying and laying DI/PVC/GI distribution system and providing FHTCs |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
AS Amount (Rs) | 367100000 |
AS Number | 777/2020/WRD |
TS Amount (Rs) | 316490000 |
TS Number | 14727/2020-2021 |
Total Bill Submitted (Rs) | 32312308 |
Total Bill Paid (Rs) | 32312308 |
Population Benefitted | 28718 |
Capacity in MLD | 12.00 |
Actual Project Completion Date | 08 Feb 2022 |
Coverage | Ayarkunnam Panchayath area |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | JJM-WSS to Ayarkunnam Panchayath Package 1-Supplying and laying DI/PVC/GI distribution system and providing FHTCs in 2 zones | Kottayam Project Dn | |
2 | JJM-WSS to Ayarkunnam Panchayath Package 2 | Kottayam Project Dn | |
3 | JJM-WSS to Ayarkunnam Panchayath Package 3 | Kottayam Project Dn | |
4 | JJM-WSS to Ayarkunnam Panchayath Package 4 | Kottayam Project Dn |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Feb 2024 | 53km laying completed out of 166km.1519 connections given out of 7820 connections. Construction work of Tranformer room completed.750kVA transformer supplied. | Kottayam AE 3 | |
27 Jul 2022 | Meeting at Ayarkunnam panchayath was held on 20.07.2022 panchayath authorities KWA EE,AEE,AE,ISA and JJM staff attended the meating to discuss the progress and issues in on going JJM works. | Kottayam AE 3 | |
04 Feb 2022 | In Package 1, 9km 90mm PVC Pipe laid out of 61km. | Kottayam AE 3 | |
08 Nov 2021 | In Package 1, 4km 90mm PVC Pipe laid out of 41km.Pipe laying and connection work progressing in Panchayath roads.PWD road cutting permission pending in 3 reaches. Road restoration amount remitted for 9 reaches. Agreement not executed .Letter given to contractor on 27-10-2021 to supply pipe materials for laying in those PWD roads. Package 2- Sub station room roof slab concreting work completed. Now FHTC work progressing in panchayath roads. In Package 4 ,2.4km pvc pipe laid out of 6 km | Kottayam AE 3 | |
07 Nov 2021 | 4km/41km pipe laid and 493/7820 FHTC given | Kottayam AE 3 |
Review Date | Review Message | Review Attended By |
---|---|---|
03 Feb 2021 | project components ,officers in charge etc to be added |
Date of start of Project | 04/02/2021 |
---|---|
Scheduled date of Completion of the Project | 06 Feb 2022 |
Expected date of Completion | 25/03/2024 |
AS Date | 24 Dec 2020 |
---|---|
TS Date | 16 Jan 2021 |
Project Officers | View |
---|