Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Aug 2021 | Package I-Pipe not supplied at site,Package II-No work,Package III-Work completed,Package IV-90mm PVC laying progressing -39m | Kottayam AE 3 | |
16 Aug 2021 | Package 1- letter given to contractor on 11/08/2021 regarding delay in starting the work. | Kottayam AE 3 | |
12 Aug 2021 | Package I-Pipe not supplied at site,Package II-No work,Package III-Work completed,Package IV-90mm PVC laying progressing in Kunnumpuram area | Kottayam AE 3 | |
11 Aug 2021 | Package I-Pipe not supplied at site,Package II-No work,Package III-Work completed,Package IV-90mm PVC laying in progress (78m) | Kottayam AE 3 | |
10 Aug 2021 | Package 2-No work, Package 4-90mm PVC pipe laying in progress (156m) Kunnumpuram area | Kottayam AE 3 | |
08 Aug 2021 | Package2- No work,Package 4 - 90mm PVC pipe laying in progress (74m) | Kottayam AE 3 | |
25 Jul 2021 | Package 2-No work | Kottayam AE 3 | |
22 Jul 2021 | No work | Kottayam AE 3 | |
15 Jul 2021 | Package 2-No work | Kottayam AE 3 | |
30 Jun 2021 | Package 2-Fabrication works of panel boards in progress | Kottayam AE 3 |