Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Jun 2021 | Contacted ISA(Solidarity Movement of India) . Agreement not executed | Kottayam AE 3 | |
28 Jun 2021 | Package 1 Agreement executed on 28-06-2021 | Kottayam AE 3 | |
27 May 2021 | 80 connections given in Ayarkunnam Panchayath | Kottayam AE 3 | |
14 May 2021 | Work order for package 1 on 7-05-2021 | Kottayam AE 3 | |
18 Apr 2021 | Package 1-Single bid received. submitted to CE's office for prequalification | Kottayam AE 3 | |
18 Apr 2021 | Single bid received. submitted to CE's office for prequalification | Kottayam AE 3 | |
24 Feb 2021 | Received list for FHTC from Pt authorities | Kottayam AE 3 | |
23 Feb 2021 | Joint inspection conducted with EE , AEE and contractor at site for the construction of Transformer room. | Kottayam AE 3 | |
22 Feb 2021 | Agreement executed, Purchase order placed for USS transformer, | Kottayam AE 3 | |
15 Feb 2021 | Package I-No bids received on first tender. Retendered | Kottayam AE 3 |