Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Jun 2024 | Total pipe Laying - 29537m. Total connection =425nos.Tagged-185 nos | Ollur AE | |
30 Apr 2024 | Total pipe Laying - 29537m. Total connection =240 | Ollur AE | |
06 Apr 2024 | Total pipe Laying - 28027m. Total connection =240 | Ollur AE | |
21 Mar 2024 | Total pipe Laying - 28027m. Total connection =240 | Ollur AE | |
08 Jan 2024 | Total pipe Laying - 28027m. Total connection -170 | Ollur AE | |
30 Nov 2023 | CC 9th & Final Bill Submitted | Ollur AE | |
25 Nov 2023 | CC 9th & Final Bill Submitted | Ollur AE | |
26 Oct 2023 | CC 9th & Final Bill Submitted | Ollur AE | |
04 Oct 2023 | CC 9th & Final Bill Submitted | Ollur AE | |
29 Jul 2023 | CC 9th & Final Bill Submitted | Ollur AE |