Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Aug 2021 (1) App: 12D-providing WSC from existing pipe(retrofitting)-1435 FHTCs- 50 % completed, CC 5th & part bill submitted, (2) App 12A-Distribution strengthening-not started Chalakudy AEE
20 Jul 2021 Bill of motor pumpset submitted Irinjalakkuda PH Dn EE
12 Jul 2021 First and final bill Submitted Rs. 1134560/- Appendix 12 C- Motor pump set (WTP) Irinjalakkuda PH Dn EE
08 Jul 2021 First and final bill Submitted Rs. 1134560/- Appendix 12 C- Motor pump set (WTP) Irinjalakkuda PH Dn EE
06 Jul 2021 First and final bill Submitted Rs. 1134560/- Appendix 12 C- Motor pump set (WTP) Irinjalakkuda PH Dn EE
02 Jul 2021 First and final bill Submitted Rs. 1134560/- Appendix 12 C- Motor pump set (WTP) Irinjalakkuda PH Dn EE
30 Jun 2021 First and final bill Submitted Rs. 1134560/- Appendix 12 C- Motor pump set (WTP) Irinjalakkuda PH Dn EE
29 Jun 2021 First and final bill Submitted Rs. 1134560/- Appendix 12 C- Motor pump set (WTP) Irinjalakkuda PH Dn EE
25 Jun 2021 First and final bill Submitted Rs. 1134560/- Appendix 12 C- Motor pump set (WTP) Irinjalakkuda PH Dn EE
23 Jun 2021 First and final bill Submitted Rs. 1134560/- Appendix 12 C- Motor pump set (WTP) Irinjalakkuda PH Dn EE