JAL JEEVAN MISSION 2020-21- THRIKKUR GRAMA PANCHAYATH - Providing FHTC to Rural house holds, Retrofitting , Augmentation of Existing Rural Water Supply Schemes

Project JAL JEEVAN MISSION 2020-21- THRIKKUR GRAMA PANCHAYATH - Providing FHTC to Rural house holds, Retrofitting , Augmentation of Existing Rural Water Supply Schemes
Project Code TCRJJM07203874
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JAL JEEVAN MISSION 2020-21- THRIKKUR GRAMA PANCHAYATH - Providing FHTC to Rural house holds, Retrofitting , Augmentation of Existing Rural Water Supply Schemes
Status On-going
District Thrissur
Executing Office Ollur Sn
AS Amount (Rs) 46300000
AS Number G.O.(Rt)No.541/2020/WRD
TS Amount (Rs) 46200000
TS Number TS/2020-2021/2020/13451
Total Bill Submitted (Rs) 38970507
Total Bill Paid (Rs) 38970507
Population Benefitted 11175
Capacity in MLD 3.00
Actual Project Completion Date Date is not specified
Coverage Thrikkur Pt
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jalajeevan Mission-2020-21- Thrikkur Grama panchayath-Appendix 12 C- Motor pump set (WTP) Ollur Sn
2 JAL JEEVAN MISSION 2020-21- THRIKKUR GRAMA PANCHAYATH (APPENDIX 12 C) - Providing FHTC to Rural house holds, Retrofitting , Augmentation of Existing Rural Water Supply Schemes PH.Division Irinjalakkuda
3 Jal Jeevan Mission(JJM)-RWSS to Thrikkur- Pipe line Extension at Kottayi Canal Chungam Road Through Jal Jeevan Mission Ollur Sn
4 JJM-2020-21-Thrikkur grama panchayath-APP;12A-Distribution strengthening. Ollur Sn
5 JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation Ollur Sn
6 JJM Thrikkur panchayath 2020-21 - App:12D-providing WSC from existing pipe(retrofitting)-1435 FHTCs Ollur Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Jun 2024 Total pipe Laying - 29537m. Total connection =425nos.Tagged-185 nos Ollur AE
30 Apr 2024 Total pipe Laying - 29537m. Total connection =240 Ollur AE
06 Apr 2024 Total pipe Laying - 28027m. Total connection =240 Ollur AE
21 Mar 2024 Total pipe Laying - 28027m. Total connection =240 Ollur AE
08 Jan 2024 Total pipe Laying - 28027m. Total connection -170 Ollur AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 05/09/2020
Scheduled date of Completion of the Project 08 May 2021
Expected date of Completion 31/12/2022

Processing Dates

AS Date 21 Aug 2020
TS Date 05 Sep 2020

Other details

Project Officers View