Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Jul 2023 CC 9th & Final Bill Submitted Ollur AE
14 Jul 2023 CC 9th & Final Bill Submitted Ollur AE
10 Jul 2023 CC 9th & Final Bill Submitted Ollur AE
04 Jul 2023 CC 9th & Final Bill Submitted Ollur AE
30 Jun 2023 JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation- work in progress Ollur AE
24 Jun 2023 JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation- work in progress Ollur AE
19 Jun 2023 JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation- work in progress Ollur AE
14 Jun 2023 JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation- work in progress Ollur AE
05 Jun 2023 JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation- work in progress Ollur AE
01 Jun 2023 JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation- work in progress Ollur AE