Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Jul 2023 | CC 9th & Final Bill Submitted | Ollur AE | |
14 Jul 2023 | CC 9th & Final Bill Submitted | Ollur AE | |
10 Jul 2023 | CC 9th & Final Bill Submitted | Ollur AE | |
04 Jul 2023 | CC 9th & Final Bill Submitted | Ollur AE | |
30 Jun 2023 | JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation- work in progress | Ollur AE | |
24 Jun 2023 | JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation- work in progress | Ollur AE | |
19 Jun 2023 | JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation- work in progress | Ollur AE | |
14 Jun 2023 | JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation- work in progress | Ollur AE | |
05 Jun 2023 | JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation- work in progress | Ollur AE | |
01 Jun 2023 | JJM Thrikkur panchayath 2020-21 - App:12b & 12E-pipeline extension to various wards and providing WSC after augmentation- work in progress | Ollur AE |