Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
05 Nov 2021 | Work on progress | Irinjalakuda AE | |
03 Nov 2021 | 922 FHTC provided | Irinjalakuda AE | |
01 Nov 2021 | 907 FHTC provided | Irinjalakuda AE | |
25 Oct 2021 | 871 FHTC provided and bill for 137 FHTC submitted | Irinjalakuda AE | |
21 Oct 2021 | Work is interrupted due to rise in water table | Irinjalakuda AE | |
18 Oct 2021 | Work is interrupted due to rise in water table | Irinjalakuda AE | |
14 Oct 2021 | 852 FHTC provided | Irinjalakuda AE | |
11 Oct 2021 | Work on progress | Irinjalakuda AE | |
06 Oct 2021 | 815 FHTC provided | Irinjalakuda AE | |
04 Oct 2021 | 787 FHTC provided | Irinjalakuda AE |