Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Apr 2022 | 1525 FHTC PROVIDED | Irinjalakuda AE | |
19 Apr 2022 | 1497 FHTC PROVIDED | Irinjalakuda AE | |
14 Apr 2022 | 1497 FHTC PROVIDED | Irinjalakuda AE | |
11 Apr 2022 | 1482 FHTC PROVIDED | Irinjalakuda AE | |
08 Apr 2022 | 1480 FHTC PROVIDED | Irinjalakuda AE | |
05 Apr 2022 | 1468 FHTC PROVIDED | Irinjalakuda AE | |
01 Apr 2022 | 1468 FHTC PROVIDED | Irinjalakuda AE | |
28 Mar 2022 | 1468 FHTC PROVIDED | Irinjalakuda AE | |
22 Mar 2022 | 1449 FHTC PROVIDED | Irinjalakuda AE | |