Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 Apr 2023 | 88% work completed | Irinjalakuda AE | |
03 Feb 2023 | 86% work completed | Irinjalakuda AE | |
16 Dec 2022 | Providing FHTC is in progress at padiyur GP. | Irinjalakuda AE | |
06 Dec 2022 | Providing FHTC is in progress at padiyur GP. | Irinjalakuda AE | |
26 Nov 2022 | Providing FHTC is in progress at padiyur GP. | Irinjalakuda AE | |
28 Oct 2022 | Work temporarily stopped due to water logging | Irinjalakuda AE | |
20 Oct 2022 | Work temporarily stopped due to water clogging | Irinjalakuda AE | |
29 Aug 2022 | Work temporarily stopped due to water clogging | Irinjalakuda AE | |
14 Jun 2022 | 1580 FHTC PROVIDED and 9th and part bill submitted | Irinjalakuda AE | |