Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 Jul 2021 | 702 FHTC provided, 2 part bills are submitted. | Irinjalakkuda PH Dn EE | |
05 Jul 2021 | 702 FHTC provided, 2 part bills are submitted. | Irinjalakkuda PH Dn EE | |
02 Jul 2021 | 702 FHTC provided, 2 part bills are submitted. | Irinjalakkuda PH Dn EE | |
30 Jun 2021 | 702 FHTC provided, 2 part bills are submitted. | Irinjalakkuda PH Dn EE | |
29 Jun 2021 | 702 FHTC provided, 2 part bills are submitted. | Irinjalakkuda PH Dn EE | |
28 Jun 2021 | 702 FHTC provided, 2 part bills are submitted. | Irinjalakkuda PH Dn EE | |
25 Jun 2021 | 678 FHTC provided, 2 part bills are submitted. | Irinjalakkuda PH Dn EE | |
23 Jun 2021 | 633 FHTC provided, 2 part bills are submitted. | Irinjalakkuda PH Dn EE | |
21 Jun 2021 | 633 FHTC provided, 2 part bills are submitted. | Irinjalakkuda PH Dn EE | |
15 Jun 2021 | 577 FHTC provided, 2 part bills are submitted. | Irinjalakkuda PH Dn EE |