Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Jul 2021 702 FHTC provided, 2 part bills are submitted. Irinjalakkuda PH Dn EE
05 Jul 2021 702 FHTC provided, 2 part bills are submitted. Irinjalakkuda PH Dn EE
02 Jul 2021 702 FHTC provided, 2 part bills are submitted. Irinjalakkuda PH Dn EE
30 Jun 2021 702 FHTC provided, 2 part bills are submitted. Irinjalakkuda PH Dn EE
29 Jun 2021 702 FHTC provided, 2 part bills are submitted. Irinjalakkuda PH Dn EE
28 Jun 2021 702 FHTC provided, 2 part bills are submitted. Irinjalakkuda PH Dn EE
25 Jun 2021 678 FHTC provided, 2 part bills are submitted. Irinjalakkuda PH Dn EE
23 Jun 2021 633 FHTC provided, 2 part bills are submitted. Irinjalakkuda PH Dn EE
21 Jun 2021 633 FHTC provided, 2 part bills are submitted. Irinjalakkuda PH Dn EE
15 Jun 2021 577 FHTC provided, 2 part bills are submitted. Irinjalakkuda PH Dn EE