Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
10 Jun 2021 | 505 FHTC provided, 2 part bills are submitted. | Irinjalakkuda PH Dn EE | |
01 Jun 2021 | 505 FHTC provided, 2 part bills are submitted. | Irinjalakkuda PH Dn EE | |
30 May 2021 | 1000 FHTC Provided. 50% completed. | Irinjalakkuda PH Dn EE | |
23 May 2021 | First and second part bill Paid 3228224/-(1674432&1553792/-). | Irinjalakkuda PH Dn EE | |
17 May 2021 | First and second part bill Paid 3228224/-(1674432&1553792/-). | Irinjalakkuda PH Dn EE | |
06 May 2021 | First and second part bill Paid 3228224/-(1674432&1553792/-). | Irinjalakkuda PH Dn EE | |
29 Apr 2021 | 24% completed, 476 FHTC provided. | Irinjalakkuda PH Dn EE | |
19 Mar 2021 | 254 nos completed | Irinjalakkuda PH Dn EE | |
04 Mar 2021 | Total numbers of fhtc provided as on 3.3.2021 - 144nos. | Irinjalakkuda PH Dn EE | |
13 Feb 2021 | AE reported that, geotagging cannot be done , since contractor not istalled water meter at connection points. direction issued to the contractor on 2.2.2021. Fhtc provided as on 12.2.2021 is 36nos/1972 | Irinjalakkuda PH Dn EE |