Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Jun 2021 505 FHTC provided, 2 part bills are submitted. Irinjalakkuda PH Dn EE
01 Jun 2021 505 FHTC provided, 2 part bills are submitted. Irinjalakkuda PH Dn EE
30 May 2021 1000 FHTC Provided. 50% completed. Irinjalakkuda PH Dn EE
23 May 2021 First and second part bill Paid 3228224/-(1674432&1553792/-). Irinjalakkuda PH Dn EE
17 May 2021 First and second part bill Paid 3228224/-(1674432&1553792/-). Irinjalakkuda PH Dn EE
06 May 2021 First and second part bill Paid 3228224/-(1674432&1553792/-). Irinjalakkuda PH Dn EE
29 Apr 2021 24% completed, 476 FHTC provided. Irinjalakkuda PH Dn EE
19 Mar 2021 254 nos completed Irinjalakkuda PH Dn EE
04 Mar 2021 Total numbers of fhtc provided as on 3.3.2021 - 144nos. Irinjalakkuda PH Dn EE
13 Feb 2021 AE reported that, geotagging cannot be done , since contractor not istalled water meter at connection points. direction issued to the contractor on 2.2.2021. Fhtc provided as on 12.2.2021 is 36nos/1972 Irinjalakkuda PH Dn EE