Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Jun 2024 Work temporarly stopped, due to the getting delay in RE sanction.Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
26 Jun 2024 Work temporarly stopped, due to the getting delay in RE sanction.Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
25 Jun 2024 Work temporarly stopped, due to the getting delay in RE sanction.Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
24 Jun 2024 Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction Sasthamcotta WS Sn 1 - AE
20 Jun 2024 Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction Sasthamcotta WS Sn 1 - AE
12 Jun 2024 Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction Sasthamcotta WS Sn 1 - AE
10 Jun 2024 Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Sasthamcotta WS Sn 1 - AE
05 Jun 2024 Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Sasthamcotta WS Sn 1 - AE
01 Jun 2024 Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction Sasthamcotta WS Sn 1 - AE
28 May 2024 Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction Sasthamcotta WS Sn 1 - AE