Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Feb 2024 | Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Waiting for RE sanction. | Sasthamcotta WS Sn 1 - AE | |
14 Feb 2024 | Road restoration work in various wards work in progress . 77% of work completed. | Sasthamcotta WS Sn 1 - AE | |
11 Feb 2024 | Road restoration work in various wards work in progress . 77% of work completed. | Sasthamcotta WS Sn 1 - AE | |
08 Feb 2024 | Road restoration work in variuos wards work in progress . 77% of work completed. | Sasthamcotta WS Sn 1 - AE | |
31 Jan 2024 | Road restoration work in variuos wards work in progress . 77% of work completed. | Sasthamcotta WS Sn 1 - AE | |
27 Jan 2024 | 77 % of work completed. | Sasthamcotta WS Sn 1 - AE | |
22 Jan 2024 | 77 % of work completed. | Sasthamcotta WS Sn 1 - AE | |
16 Jan 2024 | 77 % of work completed. | Sasthamcotta WS Sn 1 - AE | |
11 Jan 2024 | Road restoration work in variuos wards work in progress | Sasthamcotta WS Sn 1 - AE | |
07 Jan 2024 | Work in progress . 77 % of work completed | Sasthamcotta WS Sn 1 - AE |