Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Apr 2024 | Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. | Sasthamcotta WS Sn 1 - AE | |
24 Apr 2024 | Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. | Sasthamcotta WS Sn 1 - AE | |
22 Apr 2024 | Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction | Sasthamcotta WS Sn 1 - AE | |
09 Apr 2024 | Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction | Sasthamcotta WS Sn 1 - AE | |
27 Mar 2024 | Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. | Sasthamcotta WS Sn 1 - AE | |
21 Mar 2024 | Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. | Sasthamcotta WS Sn 1 - AE | |
04 Mar 2024 | Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. | Sasthamcotta WS Sn 1 - AE | |
29 Feb 2024 | Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Waiting for RE sanction. | Sasthamcotta WS Sn 1 - AE | |
24 Feb 2024 | Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Waiting for RE sanction. | Sasthamcotta WS Sn 1 - AE | |
20 Feb 2024 | Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Waiting for RE sanction. | Sasthamcotta WS Sn 1 - AE |