27 Apr 2024 Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Sasthamcotta WS Sn 1 - AE
24 Apr 2024 Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Sasthamcotta WS Sn 1 - AE
22 Apr 2024 Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction Sasthamcotta WS Sn 1 - AE
09 Apr 2024 Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction Sasthamcotta WS Sn 1 - AE
27 Mar 2024 Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Sasthamcotta WS Sn 1 - AE
21 Mar 2024 Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Sasthamcotta WS Sn 1 - AE
04 Mar 2024 Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Sasthamcotta WS Sn 1 - AE
29 Feb 2024 Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Waiting for RE sanction. Sasthamcotta WS Sn 1 - AE
24 Feb 2024 Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Waiting for RE sanction. Sasthamcotta WS Sn 1 - AE
20 Feb 2024 Out of 11 km - 10.20 km laying work completed. Road restoration work completed. Waiting for RE sanction. Sasthamcotta WS Sn 1 - AE