Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 May 2024 | Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction | Sasthamcotta WS Sn 1 - AE | |
20 May 2024 | Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. | Sasthamcotta WS Sn 1 - AE | |
16 May 2024 | Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. | Sasthamcotta WS Sn 1 - AE | |
14 May 2024 | Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction | Sasthamcotta WS Sn 1 - AE | |
10 May 2024 | Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. | Sasthamcotta WS Sn 1 - AE | |
07 May 2024 | Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. | Sasthamcotta WS Sn 1 - AE | |
06 May 2024 | Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction | Sasthamcotta WS Sn 1 - AE | |
04 May 2024 | Out of 11 km - 10.20 km laying work completed. Road restoration work completed.Work temporarly stopped, waiting for RE sanction | Sasthamcotta WS Sn 1 - AE | |
02 May 2024 | Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. | Sasthamcotta WS Sn 1 - AE | |
29 Apr 2024 | Work temporarly stopped. Waiting for RE sanction. Out of 11 km - 10.20 km laying work completed. Road restoration work completed. | Sasthamcotta WS Sn 1 - AE |