| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Nov 2024 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work,quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender.Recast the estimate is progressing | Kochi WS Dn EE | |
| 21 Nov 2024 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work,quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender.Recast the estimate is progressing | North Paravoor WS Sn - AE | |
| 18 Nov 2024 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work,quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender.Recast the estimate is progressing | North Paravoor WS Sn - AE | |
| 15 Nov 2024 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work,quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender.Recast the estimate is progressing | Kochi WS Dn EE | |
| 13 Nov 2024 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work,quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender.Recast the estimate is progressing | North Paravoor WS Sn - AE | |
| 11 Nov 2024 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work,quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender.Recast the estimate is progressing | North Paravoor WS Sn - AE | |
| 11 Nov 2024 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work,quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender.Recast the estimate is progressing. | Kochi WS Dn EE | |
| 08 Nov 2024 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work,quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender.Recast the estimate is progressing. | North Paravoor WS Sn - AE | |
| 06 Nov 2024 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work,quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender.Recast the estimate is progressing. | North Paravoor WS Sn - AE | |
| 04 Nov 2024 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender.Recast the estimate is progressing. | Kochi WS Dn EE |