| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Aug 2024 | Package-I work in progress. Package 2- work spilt up and tendered for the supply of motor pump set due date on .21-08-2024 | North Paravoor WS Sn - AE | |
| 29 Aug 2024 | Package-I work in progress. Package 2- work spilt up and tendered for the supply of motor pump set due date on .21-08-2024 | North Paravoor WS Sn - AE | |
| 27 Aug 2024 | Package-I work in progress. Package 2- work spilt up and tendered for the supply of motor pump set due date on .21-08-2024 | North Paravoor WS Sn - AE | |
| 24 Aug 2024 | Package-I work in progress. Package 2- work spilt up and tendered for the supply of motor pump set due date on .21-08-2024 | North Paravoor WS Sn - AE | |
| 21 Aug 2024 | Package-I work in progress. Package 2- work spilt up and tendered for the supply of motor pump set due date on .21-08-2024 | North Paravoor WS Sn - AE | |
| 17 Aug 2024 | Package-I work in progress. Package 2- work spilt up and tendered for the supply of motor pump set due date on .21-08-2024 | North Paravoor WS Sn - AE | |
| 14 Aug 2024 | Package-I Transformer Erected. Package 2- work spilt up and tendered for the supply of motor pump set due date on .21-08-2024 | North Paravoor WS Sn - AE | |
| 12 Aug 2024 | Package-I Retendered Due dt on 24.6.2024,Wrk order issued on 8.7.2024,Agreement executed, Transformer supplied. Package 2- work spilt up and tendered for the supply of motor pump set due date on .21-08-2024 | Kochi WS Dn EE | |
| 12 Aug 2024 | Package-I Retendered Due dt on 24.6.2024,Wrk order issued on 8.7.2024.Agreement executed. Work started | Kochi WS Dn EE | |
| 16 Apr 2024 | The work tendered as per tender no.80/2023-24-due date on 18.3.2024 no offer received. hence date extended Two times. No offer received | Kochi WS Dn EE |