| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Mar 2025 | As the quoted rate is above the LMR rate cancelled the tender. Recast the Estimate is progressing | Kochi WS Dn EE | |
| 17 Mar 2025 | As the quoted rate is above the LMR rate cancelled the tender. Recast the Estimate is progressing | North Paravoor WS Sn - AE | |
| 14 Mar 2025 | As the quoted rate is above the LMR rate cancelled the tender. Recast the Estimate is progressing | North Paravoor WS Sn - AE | |
| 13 Mar 2025 | As the quoted rate is above the LMR rate cancelled the tender. Recast the Estimate is progressing | Kochi WS Dn EE | |
| 11 Mar 2025 | As the quoted rate is above the LMR rate cancelled the tender. Recast the Estimate is progressing | North Paravoor WS Sn - AE | |
| 05 Mar 2025 | As the quoted rate is above the LMR rate cancelled the tender. Recast the Estimate is progressing | Kochi WS Dn EE | |
| 01 Mar 2025 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work, quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender. Recast the estimate is progressing | Kochi WS Dn EE | |
| 27 Feb 2025 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work, quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender. Recast the estimate is progressing | North Paravoor WS Sn - AE | |
| 25 Feb 2025 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work, quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender. Recast the estimate is progressing | Kochi WS Dn EE | |
| 21 Feb 2025 | Package -I Transformer work 95% completed, Approval from KEI obtained Charging work pending. Package 2A Replacement of Motor pump house Agreement executed on 27.9.2024. Package 2B Sluice valve Direction given to sub division for arrange the work, quotation invited. Package 2c Solar panel As the quoted rate is above the LMR rate cancelled the tender. Recast the estimate is progressing | Kochi WS Dn EE |