Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Apr 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
08 Apr 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
06 Apr 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
05 Apr 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
04 Apr 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
03 Apr 2024 913 connections given and 913 no.s geotagged. Pipe laying works on progress. Already laid 63mm PVC - 3504.40m & 75mm PVC - 1704.40m Chathannur PH Sn AE
02 Apr 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
01 Apr 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
30 Mar 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
27 Mar 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE