Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Jul 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
01 Jul 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
29 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
28 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
26 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
25 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
22 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
21 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
20 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
19 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE