Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Jul 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
01 Jul 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
29 Jun 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
28 Jun 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
26 Jun 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
25 Jun 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
22 Jun 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
21 Jun 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
20 Jun 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
19 Jun 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE |