Jal Jeevan Mission (JJM)-JJM 2022-23- POOTHAKKULAM PANCHAYATH PHASE 2 (PART)-Jal Jeevan Mission Phase- I- Balance work in Poothakkulam Panchayath.-Pipeline Work

Project Jal Jeevan Mission (JJM)-JJM 2022-23- POOTHAKKULAM PANCHAYATH PHASE 2 (PART)-Jal Jeevan Mission Phase- I- Balance work in Poothakkulam Panchayath.-Pipeline Work
Project Code KLMJJM082014881
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission -JJM 2022-23- POOTHAKKULAM PANCHAYATH PHASE 2 (PART)-Jal Jeevan Mission Phase- I- Balance work in Poothakkulam Panchayath.-Pipeline Work
Status On-going
District Kollam
Executing Office Kollam PH Dn
AS Amount (Rs) 32124000
AS Number G.O.(Rt)No.541/2020/WRD
TS Amount (Rs) 3000000
TS Number WRD/KWA-CE(SR)/EST_TS/17658/2023_26_1_1
Total Bill Submitted (Rs) 1325081
Total Bill Paid (Rs) 0
Population Benefitted 3000
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage It is for the gap filling work of the existing JICA pipe line at Kottuvankonam market to Chakkuvila road in the Poothakkulam Grama Panchayath. And for replacement of old AC pipe line in Poothakkulam Panchayath.

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-JJM 2022-23- POOTHAKKULAM PANCHAYATH PHASE 2 (PART)-Jal Jeevan Mission Phase- I- Balance work in Poothakkulam Panchayath Chathannoor PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
28 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
26 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
25 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
22 Jun 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 11/08/2023
Scheduled date of Completion of the Project 10 Dec 2023
Expected date of Completion 10/12/2023

Processing Dates

AS Date 21 Aug 2020
TS Date 15 Sep 2023

Other details

Project Officers View