Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 May 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
22 May 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
21 May 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
20 May 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
18 May 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
17 May 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
14 May 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
13 May 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
09 May 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
08 May 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE |