Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 May 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
22 May 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
21 May 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
20 May 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
18 May 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
17 May 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
14 May 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
13 May 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
09 May 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
08 May 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE