Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Feb 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock. | Chathannur PH Sn AE | |
14 Feb 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
13 Feb 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
12 Feb 2024 | 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
08 Feb 2024 | 90mm PVC pipe laying work in progress -654m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 270m. Excavation is done in Ordinary Rock | Chathannur PH Sn AE | |
07 Feb 2024 | 90mm PVC pipe laying work in progress -574m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 190m. Excavation is done in Ordinary Rock. | Chathannur PH Sn AE | |
05 Feb 2024 | 90mm PVC pipe laying work in progress -384m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 42m. Excavation is done in Ordinary Rock. | Chathannur PH Sn AE | |
03 Feb 2024 | 90mm PVC pipe laying work in progress -384m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress. Excavation is done in Ordinary Rock. | Chathannur PH Sn AE | |
02 Feb 2024 | 90mm PVC pipe laying work in progress -384m completed & GSB for tar road filling work started. 160mm PVC pipe laying started. | Chathannur PH Sn AE | |
01 Feb 2024 | 90mm PVC pipe laying work in progress -384m completed & GSB for tar road filling work started. 160mm PVC pipe laying started. | Chathannur PH Sn AE |