Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Feb 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock. Chathannur PH Sn AE
14 Feb 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
13 Feb 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
12 Feb 2024 90mm PVC pipe laying work in progress -659m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 275m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
08 Feb 2024 90mm PVC pipe laying work in progress -654m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 270m. Excavation is done in Ordinary Rock Chathannur PH Sn AE
07 Feb 2024 90mm PVC pipe laying work in progress -574m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 190m. Excavation is done in Ordinary Rock. Chathannur PH Sn AE
05 Feb 2024 90mm PVC pipe laying work in progress -384m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress - 42m. Excavation is done in Ordinary Rock. Chathannur PH Sn AE
03 Feb 2024 90mm PVC pipe laying work in progress -384m completed & GSB for tar road filling work started. 160mm PVC pipe laying work in progress. Excavation is done in Ordinary Rock. Chathannur PH Sn AE
02 Feb 2024 90mm PVC pipe laying work in progress -384m completed & GSB for tar road filling work started. 160mm PVC pipe laying started. Chathannur PH Sn AE
01 Feb 2024 90mm PVC pipe laying work in progress -384m completed & GSB for tar road filling work started. 160mm PVC pipe laying started. Chathannur PH Sn AE