Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Nov 2023 | 150 mm DI,90mm HDPE 16 kg pipe laying at Kanjar thadipalam Road | Kattapana Project Dn AE4 | |
30 Oct 2023 | 150 mm DI,90mm HDPE 16 kg pipe laying at Kanjar thadipalam Road , 90 mm HDPE 16 kg Kolapra Kadoommackal road | Kattapana Project Dn AE4 | |
26 Oct 2023 | 150 mm DI,90mm HDPE 16 kg pipe laying at Kanjar thadipalam Road , 90 mm HDPE 16 kg Adoormala parakkattil road & 150 mm DI,90 HDPE 16 kg pipe laying at thenkumpalli kavala kaippa road | Kattapana Project Dn AE4 | |
25 Oct 2023 | zone 7-Thengumpally kavala, Kaipa road- 150 DI, 90 mmPEPN16Kg laying, node114 | Kattapana Project Dn AE4 | |
22 Oct 2023 | Zone-1 90 PEPN10 pie laying at kolapra chalappuram private road | Kattapana Project Dn AE4 | |
19 Oct 2023 | 90 mm HDPE 16 kg pipe laying at Kolapra dhwanyantharipadi road | Kattapana Project Dn AE4 | |
16 Oct 2023 | 90 mm PEPN 10 kg pipe laying in Kolapra Chalappuram Road | Kattapana Project Dn AE4 | |
12 Oct 2023 | 90 mm HDPE 16 kg laying in 7th mile kakkombu private road | Kattapana Project Dn AE4 | |
09 Oct 2023 | Package 1-Site clearing for sump at blind school Package 2 - 90mmPEPN 16kg laying in vazahakkappara road | Kattapana Project Dn AE4 | |
06 Oct 2023 | 90 mm PEPN 10 kg pipe laying in Mangombukaav Road | Kattapana Project Dn AE4 |