Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Dec 2023 | 150 mm DI & 110 mm HDPE pipe laying at Kaippa Road,90 mm HDPE 16 kg pipe laying at Nellikkunnel Adoormala road | Kattapana Project Dn AE4 | |
07 Dec 2023 | 150 mm DI & 110 mm HDPE 16 kg pipe laying at Kaippa Road | Kattapana Project Dn AE4 | |
04 Dec 2023 | Column footting completed 2.5LL sump cum pump house Kudayathoor, 90mm HDPE 16 kg pipe laying at old Moolamattom Thodupuzha road | Kattapana Project Dn AE4 | |
27 Nov 2023 | 2.5LL sump cum pump house work in progress,90 mm HDPE 16 kg pipe laying in Moolamattom Thodupuzha old Bus root, 150 mm DI & 110 mm HDPE pipe laying Kaipa Road | Kattapana Project Dn AE4 | |
23 Nov 2023 | 2.5LL sump cum pump house work in progress | Kattapana Project Dn AE4 | |
20 Nov 2023 | 150 mm DI pumping main & 110 HDPE 10 kg pipe laying at Kaipa Road & 110 HDPE 16 kg pipe laying at Kanjar Thadipalam Road | Kattapana Project Dn AE4 | |
16 Nov 2023 | 110mm HDPE 16 kg pipe laying at Thengumpillikavala Anakkayam Road | Kattapana Project Dn AE4 | |
13 Nov 2023 | PCC works at Blind school & 150 mm DI & 90 mm HDPE -16 kg pipe laying at Kanjar Thadipalam | Kattapana Project Dn AE4 | |
09 Nov 2023 | Random Rubble Masonry work at Blind school | Kattapana Project Dn AE4 | |
06 Nov 2023 | Random Rubble Masonry work at Blind school | Kattapana Project Dn AE4 |