JJM - Providing FHTC to house holds of Kudayathoor Panchayath

Project JJM - Providing FHTC to house holds of Kudayathoor Panchayath
Project Code IDKJJM022211097
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description The Project Includes Construcion of Sump cum Pumphouse, GL Tanks, Pumpsets, Pumping/Gravity mains and providing FHTC.
Status On-going
District Idukki
Executing Office Kattappana Project Dn
AS Amount (Rs) 443228000
AS Number G.O.(Rt)No.134/2022/WRD dated Thiruvananthapuram
TS Amount (Rs) 181488000
TS Number WRD/KWA-CEP/EST_TS/368/2022_5_1_1
Total Bill Submitted (Rs) 435359
Total Bill Paid (Rs) 435359
Population Benefitted 12052
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 Construction of retaining walls for various tank sites Project Division Kattapana
2 Package II- Supply and laying Distribution network and Providing FHTC to house holds of Kudayathoor Panchayath Project Division Kattapana
3 Package I -Supply and Laying Clear Water Pumping Mains, Construction of sump cum pump house, Construction of GLSR at various zones, Supply and erection of Pumpsets and Supply and erection of Transfomer Project Division Kattapana

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 May 2024 Package 1 & 2- road restoration work at thodupuzha- puliyanmala road, plastering work at 2.5 LL sump cum pump house , package 3 de shuttering work at adoormala retaining wall foundation Kattapana Project Dn AE4
15 May 2024 Package 1 & 2- 300 mm DI,150 mm DI PM & 150 mm Distribution pipe laying at Thodupuzha - Puliyananmala road, parappet work at 2.5 LL sump cum pump house,connection work, 80 mm GI pipe laying for culvert crossing , package 3 work in progress Kattapana Project Dn AE4
12 May 2024 Package 1 & 2 300 mm DI,150 mm DI PM & 150 mm Distribution pipe laying at Thodupuzha - Puliyananmala road, package 3 work in progress Kattapana Project Dn AE4
09 May 2024 Package 1 & 2 300 mm DI,150 mm DI PM & 150 mm Distribution pipe laying at Thodupuzha - Puliyananmala road, package 3 work in progress Kattapana Project Dn AE4
06 May 2024 Package 1 & 2300 mm DI,150 mm DI PM & 150 mm Distribution pipe laying at Thodupuzha - Puliyananmala road, package 3 work in progress Kattapana Project Dn AE4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/03/2023
Scheduled date of Completion of the Project 24 Mar 2024
Expected date of Completion 31/12/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 06 Aug 2022

Other details

Project Officers View