Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Jan 2024 | 150 m DI laying at Kaippa tank road,150,200 mm DI & 90 PEPN 16 laying at kolapra adoormala laying at kolapra adoormala road | Kattapana Project Dn AE4 | |
15 Jan 2024 | 150 mm DI, 200mm DI & 90 PEPN 16 laying at Kolapra adoormala road , curing done at 2.5 LL sump cum pump house blind school | Kattapana Project Dn AE4 | |
10 Jan 2024 | 1.Reinforcement Work for Sump wall& Shuttering work for Pump house Pillar 2. 80 mm GI Gap Work at Kaippa-Anakkayam Road,90 PE PN 16 Gap Work at Kaippa-Anakkayam Road | Kattapana Project Dn AE4 | |
04 Jan 2024 | Shutter removal of Haunch of sump at blind school, Connection work at kaipa junction to kaipa school road | Kattapana Project Dn AE4 | |
01 Jan 2024 | shuttering work for sump haunch at Blind school ,Kudayathoor .150 mm DI & 90 mm HDPE 16 kg laying at kudayathoor anakayam road | Kattapana Project Dn AE4 | |
28 Dec 2023 | Pump house Plinth beam curing at Blind school ,Kudayathoor,1 90 mm HDPE 16 kg laying at kaipa Karukayil colony road. | Kattapana Project Dn AE4 | |
24 Dec 2023 | Plinth beam concrete completed at Blind school, Kudayathoor | Kattapana Project Dn AE4 | |
21 Dec 2023 | 100 DI pumping main & 90 HDPE 8 kg pipe laying in shappumpady Morkadu Road | Kattapana Project Dn AE4 | |
18 Dec 2023 | Side wall reinforcement work at Blind school, Kudayathoor | Kattapana Project Dn AE4 | |
14 Dec 2023 | Plinth beam work at Blind school ,Kudayathoor.150 mm DI & 110 mm HDPE pipe laying at Kaippa Road,90 mm HDPE 16 kg pipe laying at Mani colony road | Kattapana Project Dn AE4 |