18 Jan 2024 150 m DI laying at Kaippa tank road,150,200 mm DI & 90 PEPN 16 laying at kolapra adoormala laying at kolapra adoormala road Kattapana Project Dn AE4
15 Jan 2024 150 mm DI, 200mm DI & 90 PEPN 16 laying at Kolapra adoormala road , curing done at 2.5 LL sump cum pump house blind school Kattapana Project Dn AE4
10 Jan 2024 1.Reinforcement Work for Sump wall& Shuttering work for Pump house Pillar 2. 80 mm GI Gap Work at Kaippa-Anakkayam Road,90 PE PN 16 Gap Work at Kaippa-Anakkayam Road Kattapana Project Dn AE4
04 Jan 2024 Shutter removal of Haunch of sump at blind school, Connection work at kaipa junction to kaipa school road Kattapana Project Dn AE4
01 Jan 2024 shuttering work for sump haunch at Blind school ,Kudayathoor .150 mm DI & 90 mm HDPE 16 kg laying at kudayathoor anakayam road Kattapana Project Dn AE4
28 Dec 2023 Pump house Plinth beam curing at Blind school ,Kudayathoor,1 90 mm HDPE 16 kg laying at kaipa Karukayil colony road. Kattapana Project Dn AE4
24 Dec 2023 Plinth beam concrete completed at Blind school, Kudayathoor Kattapana Project Dn AE4
21 Dec 2023 100 DI pumping main & 90 HDPE 8 kg pipe laying in shappumpady Morkadu Road Kattapana Project Dn AE4
18 Dec 2023 Side wall reinforcement work at Blind school, Kudayathoor Kattapana Project Dn AE4
14 Dec 2023 Plinth beam work at Blind school ,Kudayathoor.150 mm DI & 110 mm HDPE pipe laying at Kaippa Road,90 mm HDPE 16 kg pipe laying at Mani colony road Kattapana Project Dn AE4