Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Feb 2024 | shuttering work for beam at sump cum pump house. connection work | Kattapana Project Dn AE4 | |
20 Feb 2024 | Tree cutting done at morkad 1st booster land, connection work, shuttering work for beam at sump cum pump house. | Kattapana Project Dn AE4 | |
15 Feb 2024 | shuttering work of beam for pump house at ,150 mm DI,200 mm DI ,90 HDPE 10 kg pipe laying work at adoormala road,100 DI pumping main & 90 HDPE 16 kg pipe laying at morkadu road | Kattapana Project Dn AE4 | |
12 Feb 2024 | connection work at kanjar to anakkayam road,150,200 mm DI laying at morkkadu | Kattapana Project Dn AE4 | |
08 Feb 2024 | Work in progress | Kattapana Project Dn AE4 | |
05 Feb 2024 | Deshuttering and curing at sump cum pump,house,Connection work at kanjar thadippalam road,Zone4 100 di pumping main and 90 PEPN16 pipe laying in shappumpady morkad road. | Kattapana Project Dn AE4 | |
01 Feb 2024 | Concrete work of side wall of sump cum pump house at Blind school kudayathoor | Kattapana Project Dn AE4 | |
29 Jan 2024 | 150 DI pumping main & 200 mm DI & 90 PEPN 16 distribution pipe laying in kolapra adoormala road in Zone 1 | Kattapana Project Dn AE4 | |
25 Jan 2024 | 150 mm DI pipe laying work at Kaippa road,150 mm & 200 mm DI pipe laying work at adoormala road,80 mm GI pipe laying work at Muthiyanmala road.wall shuttering work at sump cum pump house. | Kattapana Project Dn AE4 | |
22 Jan 2024 | Blind school sump side wall shuttering, 150 mm,200 mm DI and 90 PEPN 16 laying at kolapra adoormala road | Kattapana Project Dn AE4 |