- Home
- NABARD-RIDF-XXII- Rural Water Supply Sch...
NABARD-RIDF-XXII- Rural Water Supply Scheme ( RWSS) to Arakuzha & Palakuzha Panchayaths-Phase I
Project |
NABARD-RIDF-XXII- Rural Water Supply Scheme ( RWSS) to Arakuzha & Palakuzha Panchayaths-Phase I |
Project Code |
EKMNABARD1116512 |
Type |
Main project |
Funding Agency |
NABARD |
Category |
NABARD |
Type of scheme |
Water Supply |
Scheme |
|
Description |
Rural Water Supply Scheme ( RWSS) to Arakuzha & Palakuzha Panchayaths |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Piravam Project Dn |
AS Amount (Rs) |
135000000
|
AS Number |
AS No : GO ( Rt) No 893/2016/WRD |
TS Amount (Rs) |
135000000 |
TS Number |
TS/CE/CR/KWA/35/2017-18 |
Total Bill Submitted (Rs) |
133248570 |
Total Bill Paid (Rs) |
118943000 |
Population Benefitted |
28702 |
Capacity in MLD |
5.50 |
Actual Project Completion Date |
31 Oct 2021 |
Coverage |
Arakuzha and palakuzha panchayaths |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
NABARD-RIDF-XXII-RWSS to Arakuzha and Palakuzha Panchayaths-Construction of transformer yard,4 pole structure,Erection,Testing and commisioning of 1 No KVA transformer at WTP compound,Konnanikkad in Arakuzha panchayath |
Project Division Piravom(Kattapana) |
|
2 |
NABARD-RIDF-XXII-RWSS to Arakuzha and Palakuzha Panchayaths-Supply erection trial running and commissioning of Raw water and clear water vertical Turbine/centrifugal pumpset |
Project Division Piravom(Kattapana) |
|
3 |
WSS to Arakuzha & Palakuzha Panchayath- Package- I |
Project Division Piravom(Kattapana) |
|
4 |
WSS to Arakuzha & Palakuzha Panchayath- Package- II |
Project Division Piravom(Kattapana) |
|
5 |
WSS to Arakuzha & Palakuzha Panchayath- Package- III |
Project Division Piravom(Kattapana) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Nov 2021 |
Trial running completed |
Kattappana Project Dn EE |
|
21 Oct 2021 |
Electric connection obtained to the WTP on 18.10.2021.Transformer charged in the presence of KWA and KSEB officials.Trial run of the pumpsets in the WTP also completed on the same day. |
Kattappana Project Dn EE |
|
12 Oct 2021 |
Amount as per Demand note No ECP/T2/HT/KWA-Arakkuzha/2021-22/2293 dt 07/10/2021 remiited to KSEB,for availing electrical connection |
Kattappana Project Dn EE |
|
08 Oct 2021 |
Demand note No ECP/T2/HT/KWA-Arakkuzha/2021-22/2293 dt 07/10/2021 recieved |
Kattappana Project Dn EE |
|
05 Oct 2021 |
Affidavit and request for availing power connection to the WTP at Konnanikad submitted to DCE,KSEB,Perumbavoor |
Kattappana Project Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
15/03/2018 |
Scheduled date of Completion of the Project |
31 Dec 2020 |
Expected date of Completion |
31/10/2021 |
Processing Dates
AS Date |
16 Nov 2016 |
TS Date |
02 May 2017 |