WSS to Arakuzha & Palakuzha Panchayath- Package- III

Project WSS to Arakuzha & Palakuzha Panchayath- Package- III
Project Code EKMNABARD1116512P3
Type Package
Main Project NABARD-RIDF-XXII- Rural Water Supply Scheme ( RWSS) to Arakuzha & Palakuzha Panchayaths-Phase I
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme
Description 1. Construction of 3.50 lakh litre capacity GL Sump cum pumphouse at Konnanikattu (2) Construction of 0.60 lakh litre capacity GL tank at Aroor colony (3) Construction of 1.50 lakh litre capacity GL tank at Elachikunnu (4) Supplying and laying 6 Nos Clear Water Pumping main/gravity main using 250,150 and 100 D1 K9 pipes
Status On-going
District Ernakulam
Executing Office Piravam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 135000000
TS Number TS/CE/CR/KWA/35/2017-18
Technical specification 1. Construction of 3.50 lakh litre capacity GL Sump cum pumphouse at Konnanikattu (2) Construction of 0.60 lakh litre capacity GL tank at Aroor colony (3) Construction of 1.50 lakh litre capacity GL tank at Elachikunnu (4) Supplying and laying 6 Nos Clear Water Pumping main/gravity main using 250,150 and 100 D1 K9 pipes

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 03/04/2018
Scheduled date of Completion as per agreement 15 Apr 2019
Expected date of Completion 12/04/2019

Processing Dates

TS Date 02 May 2017
Estimate Approval 02 May 2017
NIT Approval 12 May 2017
Tender Closing 31 May 2017
Technichal Pre-Qualification 06 Jun 2017
Price bid opening 17 Jun 2017

Approval Dates

Workorder Date 07 Jul 2018
NA 22 Feb 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattappana Project Dn EE
Date: 10/07/2021

Work has been completed | 100% Completed

Package completed and Final Bill Submitted.

Kattappana Project Dn EE
Date: 11/11/2020

Work has been completed | 100% Completed

Work completed.