NABARD-RIDF-XXII-RWSS to Arakuzha and Palakuzha Panchayaths-Construction of transformer yard,4 pole structure,Erection,Testing and commisioning of 1 No KVA transformer at WTP compound,Konnanikkad in Arakuzha panchayath

Project NABARD-RIDF-XXII-RWSS to Arakuzha and Palakuzha Panchayaths-Construction of transformer yard,4 pole structure,Erection,Testing and commisioning of 1 No KVA transformer at WTP compound,Konnanikkad in Arakuzha panchayath
Project Code EKMNABARD1116512P5
Type Package
Main Project NABARD-RIDF-XXII- Rural Water Supply Scheme ( RWSS) to Arakuzha & Palakuzha Panchayaths-Phase I
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme
Description -Construction of transformer yard,4 pole structure,Erection,Testing and commisioning of 1 No 250 KVA transformer at WTP compound,Konnanikkad in Arakuzha panchayath
Status On-going
District Ernakulam
Executing Office Piravam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 135000000
TS Number TS/CE/CR/KWA/35/2017-18
Technical specification -Construction of transformer yard,4 pole structure,Erection,Testing and commisioning of 1 No 250 KVA transformer at WTP compound,Konnanikkad in Arakuzha panchayath

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 29/12/2020
Scheduled date of Completion as per agreement 31 Aug 2021
Expected date of Completion 15/10/2021

Processing Dates

TS Date 20 Oct 2020
Estimate Approval 20 Oct 2020
NIT Approval 20 Oct 2020
Tender Closing 30 Oct 2020
Technichal Pre-Qualification 31 Oct 2020
Price bid opening 02 Nov 2020

Approval Dates

Workorder Date 05 Nov 2020
NA 29 Dec 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattappana Project Dn EE
Date: 01/11/2021

Work has been completed | 100% Completed

Trial running completed.

Kattappana Project Dn EE
Date: 21/10/2021

Work has been completed | 100% Completed

Electric connection obtained to the WTP on 18.10.2021.Transformer charged in the presence of KWA and KSEB officials.Trial run of the pumpsets in the WTP also completed on the same day..