Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Nov 2021 | Trial running completed | Kattappana Project Dn EE | |
21 Oct 2021 | Electric connection obtained to the WTP on 18.10.2021.Transformer charged in the presence of KWA and KSEB officials.Trial run of the pumpsets in the WTP also completed on the same day. | Kattappana Project Dn EE | |
12 Oct 2021 | Amount as per Demand note No ECP/T2/HT/KWA-Arakkuzha/2021-22/2293 dt 07/10/2021 remiited to KSEB,for availing electrical connection | Kattappana Project Dn EE | |
08 Oct 2021 | Demand note No ECP/T2/HT/KWA-Arakkuzha/2021-22/2293 dt 07/10/2021 recieved | Kattappana Project Dn EE | |
05 Oct 2021 | Affidavit and request for availing power connection to the WTP at Konnanikad submitted to DCE,KSEB,Perumbavoor | Kattappana Project Dn EE | |
20 Sep 2021 | Power Connection Application Submitted in KSEB. Trial running shall be started after obtaining power connection in WTP | Kattappana Project Dn EE | |
15 Sep 2021 | Raw water Pumpsets at Moozhi erected-Trial run completed Clear water Pumpset to Konnanikad erected at WTP Clear water pumpsets and motors for Kumbalathumala and Achakottumala supplied by the contractor-Erection work in progress | Kattappana Project Dn EE | |
16 Aug 2021 | Trial running of raw water pumpsets and raw water pumping main completed | Kattappana Project Dn EE | |
11 Jul 2021 | Inspection from Kerala Electrical Inspectorate completed for installation approval of Transformer | Kattappana Project Dn EE | |
02 Jun 2021 | Packages I,III completed.Works on WTP completed.Transformer erected.Application for electric connection submitted | Kattappana Project Dn EE |