NABARD-RIDF-XXII-RWSS to Arakuzha and Palakuzha Panchayaths-Supply erection trial running and commissioning of Raw water and clear water vertical Turbine/centrifugal pumpset

Project NABARD-RIDF-XXII-RWSS to Arakuzha and Palakuzha Panchayaths-Supply erection trial running and commissioning of Raw water and clear water vertical Turbine/centrifugal pumpset
Project Code EKMNABARD1116512P4
Type Package
Main Project NABARD-RIDF-XXII- Rural Water Supply Scheme ( RWSS) to Arakuzha & Palakuzha Panchayaths-Phase I
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme
Description Supply erection trial running and commissioning of Raw water and clear water vertical Turbine/centrifugal pumpset
Status On-going
District Ernakulam
Executing Office Piravam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 9200000
TS Number TS/CE/CR/KWA/34/2016-17
Technical specification RW VT Pumpset at Moozhi-50 HP -2set CW Centrifugal pumpsets at plant-70 HP,25 HP,15 HP-2set CW Centrifugal pumpset at pottamala-7.5HP-2set

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 08/02/2021
Scheduled date of Completion as per agreement 31 Aug 2021
Expected date of Completion 31/10/2021

Processing Dates

TS Date 30 Sep 2020
Estimate Approval 25 Aug 2020
NIT Approval 25 Aug 2020
Tender Closing 09 Sep 2020
Technichal Pre-Qualification 14 Sep 2020
Price bid opening 14 Sep 2020

Approval Dates

Workorder Date 02 Nov 2020
NA 13 Jan 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattappana Project Dn EE
Date: 01/11/2021

Work has been completed | 100% Completed

Trial running completed.

Kattappana Project Dn EE
Date: 29/10/2021

Work in progress | 98% Completed

Trial run of Raw water pumpsets at Moozhi,Clear water pumpsets at WTP etc completed..