Project | NABARD-RIDF-XXII-RWSS to Arakuzha and Palakuzha Panchayaths-Supply erection trial running and commissioning of Raw water and clear water vertical Turbine/centrifugal pumpset |
---|---|
Project Code | EKMNABARD1116512P4 |
Type | Package |
Main Project | NABARD-RIDF-XXII- Rural Water Supply Scheme ( RWSS) to Arakuzha & Palakuzha Panchayaths-Phase I |
Funding Agency | NABARD |
Category | NABARD |
Type of scheme | Water Supply |
Scheme | |
Description | Supply erection trial running and commissioning of Raw water and clear water vertical Turbine/centrifugal pumpset |
Status | On-going |
District | Ernakulam |
Executing Office | Piravam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 9200000 |
TS Number | TS/CE/CR/KWA/34/2016-17 |
Technical specification | RW VT Pumpset at Moozhi-50 HP -2set CW Centrifugal pumpsets at plant-70 HP,25 HP,15 HP-2set CW Centrifugal pumpset at pottamala-7.5HP-2set |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 08/02/2021 |
---|---|
Scheduled date of Completion as per agreement | 31 Aug 2021 |
Expected date of Completion | 31/10/2021 |
TS Date | 30 Sep 2020 |
---|---|
Estimate Approval | 25 Aug 2020 |
NIT Approval | 25 Aug 2020 |
Tender Closing | 09 Sep 2020 |
Technichal Pre-Qualification | 14 Sep 2020 |
Price bid opening | 14 Sep 2020 |
Workorder Date | 02 Nov 2020 |
---|---|
NA | 13 Jan 2021 |
Kattappana Project Dn EE |
Date: 01/11/2021 |
Work has been completed | 100% Completed
Trial running completed.
Kattappana Project Dn EE |
Date: 29/10/2021 |
Work in progress | 98% Completed