Jal Jeevan Mission-2021-22-WSS to PUTHUPALLY Panchayath in Kottayam District
Project |
Jal Jeevan Mission-2021-22-WSS to PUTHUPALLY Panchayath in Kottayam District |
Project Code |
KTMJJM09198528 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
The proposed project to Puthuppally panchayth consisting of Supply and laying 300m length 400mm DIK9 CWPM from common taping point near Keezhattukunnu to
Keezhattukunnu OHSR cum boosting station. Design and construction of 8.5LL capacity OHSR cum boosting station at Keezhattukunnu, Supply and laying 5500m length 200mm DIK9 CWPM from Keezhattukunnu OHSR cum boosting station to existing 2.4 LL capacity GLSR at Vennimala, Supply and laying CWGM 3560m length 200mm DIK9 from Keezhattukunnu OHSR to proposed 2.5LL capacity OHSR at Eravinelloor, Design and construction of 2.5LL capacity OHSR at Eramalloor, Supply and laying CWGM 200mm DIk9 5850m length from Keezhattukunnu OHSR to proposed 4.5LL capacity OHSR at Pariyaram, Design and construction of 4.50LL Capacity GLSR at Pariyaram, Supply and laying 2950m length 200mm DIK9 CWGM from Keezhattukunnu OHSR to existing 2.4 LL capacity GLSR at Kumaramkodu, Supply and erection of clear water pump sets at Keezhattukunnu boosting station for pumping to Vennimala GLSR, Supply and laying distribution network with FHTCs from above tanks. |
Status |
On-going |
District |
Kottayam |
Executing Office |
Kottayam Project Dn |
AS Amount (Rs) |
777100000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
11892000 |
TS Number |
TS/2021-2022/2021/33178 |
Total Bill Submitted (Rs) |
135347752 |
Total Bill Paid (Rs) |
135347752 |
Population Benefitted |
36238 |
Capacity in MLD |
5.33 |
Actual Project Completion Date |
03 Jan 2023 |
Coverage |
Puthupally |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :-Package III Construction of Keezhattukunnu OHSR including distribution in Keezhattukunnu zone and laying CWGM to Eravinelloor, Pariyaram, Kumaramkod and CWPM to Vennimala |
Kottayam Project Dn |
|
2 |
Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :- Package II Supplying and Laying DI / PVC / HDPE/ GI Distribution network and providing FHTCs - From Existing GLSR at Vennimala |
Kottayam Project Dn |
|
3 |
Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :- Package I Supplying and Laying DI / PVC /HDPE /GI Distribution network and providing FHTCs - From Existing GLSR at Kumaromkodu |
Kottayam Project Dn |
|
4 |
Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :-Package IV Construction of Eravinelloor OHSR and laying distribution line and providing FHTC in Eravinelloor zone |
Kottayam Project Dn |
|
5 |
Jal Jeevan Mission (JJM)-Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :Zone-V-Supplying and Laying DI / PVC /GI Distribution network and providing FHTCS - Design and construction of 4.5 LL capacity GLSR at Parackamala near Pariyaram |
Kottayam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Feb 2024 |
84 km laid out of 182 km 26 , 2681 connection given out of 8289 |
Kottayam AE 3 |
|
17 Jan 2023 |
In Package 1(Kumaramkodu Zone)17km laying completed out of 22 km .450 connections given out of 905.In Package 2(vennimala Zone)16km laying completed out of 17 km .329 connections given out of 905.In Package 3(Keezhattukunnu Zone)10km laying completed out of 69km .55 connections given.32 nos/50 nos pipe concreting completed.In Package 4(Eravianellor Zone)6km laying completed out of 62 km . 42connections . |
Kottayam AE 3 |
|
27 Jul 2022 |
Meeting at Puthuppally panchayath was held on 24.6.2022.Panchayath authorities ,KWA AEE ,AE,and ISA attended the meeting to discuss the progress and issues in On going JJM works. |
Kottayam AE 3 |
|
01 Jun 2022 |
8km laying completed out of 17.95km and 25FHTCs given out of 905FHTCs in Vennimala zone. 6km laying completed out of 22km and 125.FHTCs/905FHTCs given in Kumaramkodu zone |
Kottayam AE 3 |
|
01 Jun 2022 |
JJM review meeting for Puthuppally constituency was conducted by Hon'ble MLA Sri.Ommen Chandy sir on 5-03-22 at PWD rest house,Kottayam. |
Kottayam AE 3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
30/12/2021 |
Scheduled date of Completion of the Project |
13 Mar 2024 |
Expected date of Completion |
13/03/2024 |
Processing Dates
AS Date |
18 Sep 2019 |
TS Date |
02 Dec 2021 |