| Project | Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :-Package IV Construction of Eravinelloor OHSR and laying distribution line and providing FHTC in Eravinelloor zone |
|---|---|
| Project Code | KTMJJM09198528P4 |
| Type | Package |
| Main Project | Jal Jeevan Mission-2021-22-WSS to PUTHUPALLY Panchayath in Kottayam District |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Construction of Eravinelloor OHSR and laying distribution line and providing FHTC in Eravinelloor zone |
| Status | On-going |
| District | Kottayam |
| Executing Office | Kottayam Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 79870000 |
| TS Number | TS/2022-2023/2022/16165 |
| Technical specification | Construction of Eravinelloor OHSR and laying distribution line and providing FHTC in Eravinelloor zone |
| Contractor | Shaji K Mathew (Mob: 9447730150) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 05/08/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 04 Aug 2023 |
| Expected date of Completion | 31/03/2025 |
| TS Date | 21 Jun 2022 |
|---|---|
| Estimate Approval | 21 Jun 2022 |
| NIT Approval | 27 Jun 2022 |
| Tender Closing | 11 Jul 2022 |
| Technichal Pre-Qualification | 25 Jul 2022 |
| Price bid opening | 02 Aug 2022 |
| NA | 19 Aug 2022 |
|---|---|
| Workorder Date | 05 Aug 2022 |
| Kottayam Project Dn AE4 |
| Date: 20/04/2026 |
Work in progress | 68% Completed
laying 21.6 km completed.525 connections out of 910 provided.OHSR Structural and plastering work completed. .
| Kottayam Project Dn AE4 |
| Date: 16/04/2026 |
Work in progress | 68% Completed