Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :-Package IV Construction of Eravinelloor OHSR and laying distribution line and providing FHTC in Eravinelloor zone

Project Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :-Package IV Construction of Eravinelloor OHSR and laying distribution line and providing FHTC in Eravinelloor zone
Project Code KTMJJM09198528P4
Type Package
Main Project Jal Jeevan Mission-2021-22-WSS to PUTHUPALLY Panchayath in Kottayam District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Construction of Eravinelloor OHSR and laying distribution line and providing FHTC in Eravinelloor zone
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 79870000
TS Number TS/2022-2023/2022/16165
Technical specification Construction of Eravinelloor OHSR and laying distribution line and providing FHTC in Eravinelloor zone
Contractor Shaji K Mathew (Mob: 9447730150)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 05/08/2022
Scheduled date of Completion as per agreement 04 Aug 2023
Expected date of Completion 31/03/2025

Processing Dates

TS Date 21 Jun 2022
Estimate Approval 21 Jun 2022
NIT Approval 27 Jun 2022
Tender Closing 11 Jul 2022
Technichal Pre-Qualification 25 Jul 2022
Price bid opening 02 Aug 2022

Approval Dates

NA 19 Aug 2022
Workorder Date 05 Aug 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam Project Dn AE4
Date: 20/04/2026

Work in progress | 68% Completed

laying 21.6 km completed.525 connections out of 910 provided.OHSR Structural and plastering work completed. .

Kottayam Project Dn AE4
Date: 16/04/2026

Work in progress | 68% Completed

laying 21.6 km completed.525 connections out of 910 provided.OHSR Structural and plastering work completed. .