Jal Jeevan Mission (JJM)-Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :Zone-V-Supplying and Laying DI / PVC /GI Distribution network and providing FHTCS - Design and construction of 4.5 LL capacity GLSR at Parackamala near Pariyaram

Project Jal Jeevan Mission (JJM)-Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :Zone-V-Supplying and Laying DI / PVC /GI Distribution network and providing FHTCS - Design and construction of 4.5 LL capacity GLSR at Parackamala near Pariyaram
Project Code KTMJJM09198528P5
Type Package
Main Project Jal Jeevan Mission-2021-22-WSS to PUTHUPALLY Panchayath in Kottayam District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission (JJM)-Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :Zone-V-Supplying and Laying DI / PVC /GI Distribution network and providing FHTCS - Design and construction of 4.5 LL capacity GLSR at Parackamala near Pariyaram
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 87352267
TS Number
Technical specification Supplying and Laying DI / PVC /GI Distribution network and providing FHTCS - Design and construction of 4.5 LL capacity GLSR at Parackamala near Pariyaram

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/03/2023
Scheduled date of Completion as per agreement 19 Apr 2024
Expected date of Completion 31/12/2024

Approval Dates

Workorder Date 15 Mar 2023
NA 19 Apr 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam Project Dn AE4
Date: 20/04/2026

Work in progress | 64% Completed

laying work 23.345 km out of 34.11 km completed.448/1600 connections provided.OHSR structural and plastering work completed .

Kottayam Project Dn AE4
Date: 16/04/2026

Work in progress | 64% Completed

laying work 23.345 km out of 34.11 km completed.448/1600 connections provided.OHSR structural and plastering work completed .