Jal Jeevan Mission (JJM)-Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :Zone-V-Supplying and Laying DI / PVC /GI Distribution network and providing FHTCS - Design and construction of 4.5 LL capacity GLSR at Parackamala near Pariyaram
| Project |
Jal Jeevan Mission (JJM)-Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :Zone-V-Supplying and Laying DI / PVC /GI Distribution network and providing FHTCS - Design and construction of 4.5 LL capacity GLSR at Parackamala near Pariyaram |
| Project Code |
KTMJJM09198528P5 |
| Type |
Package |
| Main Project |
Jal Jeevan Mission-2021-22-WSS to PUTHUPALLY Panchayath in Kottayam District
|
| Funding Agency |
JJM |
| Category |
JJM |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-102-92-01 |
| Description |
Jal Jeevan Mission (JJM)-Water Supply Scheme to Puthuppally Panchayaths in
Kottayam District :Zone-V-Supplying and Laying DI / PVC /GI Distribution network and
providing FHTCS - Design and
construction of 4.5 LL capacity GLSR at Parackamala near Pariyaram |
| Status |
On-going |
| District |
Kottayam |
| Executing Office |
Kottayam Project Dn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
87352267 |
| TS Number |
|
| Technical specification |
Supplying and Laying DI / PVC /GI Distribution network and
providing FHTCS - Design and
construction of 4.5 LL capacity GLSR at Parackamala near Pariyaram |
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
15/03/2023 |
| Scheduled date of Completion as per agreement |
19 Apr 2024 |
| Expected date of Completion |
31/12/2024 |
Approval Dates
| Workorder Date |
15 Mar 2023 |
| NA |
19 Apr 2023 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Kottayam Project Dn AE4 |
| Date: 20/04/2026 |
Work in progress | 64% Completed
laying work 23.345 km out of 34.11 km completed.448/1600 connections provided.OHSR structural and plastering work completed
.
| Kottayam Project Dn AE4 |
| Date: 16/04/2026 |
Work in progress | 64% Completed
laying work 23.345 km out of 34.11 km completed.448/1600 connections provided.OHSR structural and plastering work completed
.