Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :- Package II Supplying and Laying DI / PVC / HDPE/ GI Distribution network and providing FHTCs - From Existing GLSR at Vennimala

Project Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :- Package II Supplying and Laying DI / PVC / HDPE/ GI Distribution network and providing FHTCs - From Existing GLSR at Vennimala
Project Code KTMJJM09198528P2
Type Package
Main Project Jal Jeevan Mission-2021-22-WSS to PUTHUPALLY Panchayath in Kottayam District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Supplying and Laying DI / PVC / HDPE/ GI Distribution network and providing FHTCs - From Existing GLSR at Vennimala
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 50620000
TS Number TS/2021-2022/2021/33178
Technical specification Supplying and Laying DI / PVC / HDPE/ GI Distribution network and providing FHTCs - From Existing GLSR at Vennimala
Contractor MOTTY T ULAHANNAN (Mob: 9447366903)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 30/12/2021
Scheduled date of Completion as per agreement 29 Jun 2022
Expected date of Completion 31/03/2023

Processing Dates

TS Date 02 Dec 2021
Estimate Approval 02 Dec 2021
NIT Approval 07 Dec 2021
Tender Closing 17 Dec 2021
Technichal Pre-Qualification 18 Dec 2021
Price bid opening 20 Dec 2021

Approval Dates

NA 04 Jan 2022
Workorder Date 30 Dec 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam Project Dn AE4
Date: 16/01/2025

Work has been completed | 100% Completed

Work completed.

Kottayam Project Dn AE4
Date: 15/01/2025

Work in progress | 99% Completed

Final bill submitted.