Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :-Package III Construction of Keezhattukunnu OHSR including distribution in Keezhattukunnu zone and laying CWGM to Eravinelloor, Pariyaram, Kumaramkod and CWPM to Vennimala
| Project |
Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :-Package III Construction of Keezhattukunnu OHSR including distribution in Keezhattukunnu zone and laying CWGM to Eravinelloor, Pariyaram, Kumaramkod and CWPM to Vennimala |
| Project Code |
KTMJJM09198528P3 |
| Type |
Package |
| Main Project |
Jal Jeevan Mission-2021-22-WSS to PUTHUPALLY Panchayath in Kottayam District
|
| Funding Agency |
JJM |
| Category |
JJM |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-102-92-01 |
| Description |
Construction of Keezhattukunnu OHSR including distribution in Keezhattukunnu zone and laying CWGM to Eravinelloor, Pariyaram, Kumaramkod and CWPM to Vennimala |
| Status |
On-going |
| District |
Kottayam |
| Executing Office |
Kottayam Project Dn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
296640000 |
| TS Number |
TS/2022-2023/2022/4096 |
| Technical specification |
Construction of Keezhattukunnu OHSR including distribution in Keezhattukunnu zone and laying CWGM to Eravinelloor, Pariyaram, Kumaramkod and CWPM to Vennimala |
| Contractor |
Shaji K Mathew (Mob: 9447730150) |
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
07/10/2022 |
| Scheduled date of Completion as per agreement |
09 Aug 2023 |
| Expected date of Completion |
31/12/2024 |
Processing Dates
| TS Date |
22 Jun 2022 |
| Estimate Approval |
22 Jun 2022 |
| NIT Approval |
14 Jul 2022 |
| Tender Closing |
30 Jul 2022 |
| Technichal Pre-Qualification |
01 Aug 2022 |
| Price bid opening |
05 Aug 2022 |
Approval Dates
| Workorder Date |
10 Aug 2022 |
| NA |
24 Aug 2022 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Kottayam Project Dn AE4 |
| Date: 20/04/2026 |
Work in progress | 68% Completed
OHSR-Structural work completed. Laying 38.3 km out 69.155 and pumping and gravity mains 10.5/17.510 completed.1059/2125 connections provided.
.
| Kottayam Project Dn AE4 |
| Date: 16/04/2026 |
Work in progress | 68% Completed
OHSR-Structural work completed. Laying 38.3 km out 69.155 and pumping and gravity mains 10.5/17.510 completed.1059/2125 connections provided.
.