Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :-Package III Construction of Keezhattukunnu OHSR including distribution in Keezhattukunnu zone and laying CWGM to Eravinelloor, Pariyaram, Kumaramkod and CWPM to Vennimala

Project Jal Jeevan mission-2021-2022- Water Supply Scheme to Puthuppally Panchayaths in Kottayam District :-Package III Construction of Keezhattukunnu OHSR including distribution in Keezhattukunnu zone and laying CWGM to Eravinelloor, Pariyaram, Kumaramkod and CWPM to Vennimala
Project Code KTMJJM09198528P3
Type Package
Main Project Jal Jeevan Mission-2021-22-WSS to PUTHUPALLY Panchayath in Kottayam District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Construction of Keezhattukunnu OHSR including distribution in Keezhattukunnu zone and laying CWGM to Eravinelloor, Pariyaram, Kumaramkod and CWPM to Vennimala
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 296640000
TS Number TS/2022-2023/2022/4096
Technical specification Construction of Keezhattukunnu OHSR including distribution in Keezhattukunnu zone and laying CWGM to Eravinelloor, Pariyaram, Kumaramkod and CWPM to Vennimala
Contractor Shaji K Mathew (Mob: 9447730150)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/10/2022
Scheduled date of Completion as per agreement 09 Aug 2023
Expected date of Completion 31/12/2024

Processing Dates

TS Date 22 Jun 2022
Estimate Approval 22 Jun 2022
NIT Approval 14 Jul 2022
Tender Closing 30 Jul 2022
Technichal Pre-Qualification 01 Aug 2022
Price bid opening 05 Aug 2022

Approval Dates

Workorder Date 10 Aug 2022
NA 24 Aug 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam Project Dn AE4
Date: 20/04/2026

Work in progress | 68% Completed

OHSR-Structural work completed. Laying 38.3 km out 69.155 and pumping and gravity mains 10.5/17.510 completed.1059/2125 connections provided. .

Kottayam Project Dn AE4
Date: 16/04/2026

Work in progress | 68% Completed

OHSR-Structural work completed. Laying 38.3 km out 69.155 and pumping and gravity mains 10.5/17.510 completed.1059/2125 connections provided. .