JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs

Project JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs
Project Code KNRJJM022212626
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs
Status On-going
District Kannur
Executing Office Mattannur Project Dn
AS Amount (Rs) 866900000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 866900000
TS Number 638/2022-2023
Total Bill Submitted (Rs) 151420273
Total Bill Paid (Rs) 117589235
Population Benefitted 24570
Capacity in MLD 3.00
Actual Project Completion Date 14 Dec 2023
Coverage 2928 Nos
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs -ZONE I Mattannur Project Dn
2 JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs-ZONE II Mattannur Project Dn
3 JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs -ZONE III Mattannur Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Oct 2024 earth excavation and pipe laying is in progress at keezhallur Zone1-92% work completed At keezhallur zone 2-Pipe laying in progress 15.50km completed out of 42km.Construction of sump 0.6LL capcity is in progress,overall 37% work completed At keezhallur Zone-3 Pipe laying in progress 36km pipe laid completed out of 48km.Construction 0.70LL OHSR up to plinth beam completed.over all 49% work completed Mattannur Project Sn 2 AE
26 Jun 2023 46KM Pipe laid in zone-1 of keezhallur GP & HTC work is in progress.zone-2 work has tendered.zone-3 pipe laying is in progress Mattannur Project Sn 2 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/11/2022
Scheduled date of Completion of the Project 14 Dec 2023
Expected date of Completion 31/03/2025

Processing Dates

AS Date 23 Feb 2022
TS Date 09 Dec 2022

Other details

Project Officers View