JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs-ZONE II

Project JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs-ZONE II
Project Code KNRJJM022212626P2
Type Package
Main Project JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Construction of 60000L sump cum pump house at Kotehri, 1.2 LL OHSR at Velliyamparamba , Pumping main from Kotheri to Velliyamparamba (150 mm DI K9-2500 M), Laying distribution system and 800 Nos FHTCs
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 108400000
TS Number 16819/2022-23
Technical specification Construction of 60000L sump cum pump house at Kotehri, 1.2 LL OHSR at Velliyamparamba , Pumping main from Kotheri to Velliyamparamba (150 mm DI K9-2500 M), Laying distribution system and 800 Nos FHTCs

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/09/2023
Scheduled date of Completion as per agreement 31 Mar 2024
Expected date of Completion 31/05/2025

Processing Dates

TS Date 20 Mar 2023
Estimate Approval 20 Mar 2023
NIT Approval 10 Apr 2023
Tender Closing 19 May 2023
Technichal Pre-Qualification 10 Apr 2023
Price bid opening 22 May 2023

Approval Dates

Workorder Date 31 Jul 2023
NA 21 Aug 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 12/05/2025

Work in progress | 77% Completed

Earth excavation and Pipe Laying is in progress. Total distribution is 40 km. 38 km pipe laying completed Pumping main of 150mm DI from 0.6LL sump to 1.2 LL OHSR at Velliyamparamb (2.6km) is under progress,0.75 km completed. 160 mm PVC laying at Mattannur-irikkur road completed. House connection and HTC is in progress.250 HTC completed out of 800nos.. Construction of 0.6LL SUMP cum pump house in progress at Kotheri upto cover slab completed. Pump house masonary work completed. construction of 1.2LL OHSR at Velliyamparamba up to cover slab completed. Plastering work completed.

Mattannur Project Sn 2 AE
Date: 03/05/2025

Work in progress | 75% Completed

Earth excavation and Pipe Laying is in progress. Total distribution is 40 km. 38 km pipe laying completed Pumping main of 150mm DI from 0.6LL sump to 1.2 LL OHSR at Velliyamparamb (2.6km) is under progress,0.75 km completed. 160 mm PVC laying at Mattannur-irikkur road completed. House connection and HTC is in progress.250 HTC completed out of 800nos.. Construction of 0.6LL SUMP cum pump house in progress at Kotheri upto cover slab completed. Pump house masonary work completed. construction of 1.2LL OHSR at Velliyamparamba up to cover slab completed. Plastering work in progress.