| Project | JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs-ZONE II |
|---|---|
| Project Code | KNRJJM022212626P2 |
| Type | Package |
| Main Project | JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Construction of 60000L sump cum pump house at Kotehri, 1.2 LL OHSR at Velliyamparamba , Pumping main from Kotheri to Velliyamparamba (150 mm DI K9-2500 M), Laying distribution system and 800 Nos FHTCs |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 108400000 |
| TS Number | 16819/2022-23 |
| Technical specification | Construction of 60000L sump cum pump house at Kotehri, 1.2 LL OHSR at Velliyamparamba , Pumping main from Kotheri to Velliyamparamba (150 mm DI K9-2500 M), Laying distribution system and 800 Nos FHTCs |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 01/09/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 31 Mar 2024 |
| Expected date of Completion | 31/05/2025 |
| TS Date | 20 Mar 2023 |
|---|---|
| Estimate Approval | 20 Mar 2023 |
| NIT Approval | 10 Apr 2023 |
| Tender Closing | 19 May 2023 |
| Technichal Pre-Qualification | 10 Apr 2023 |
| Price bid opening | 22 May 2023 |
| Workorder Date | 31 Jul 2023 |
|---|---|
| NA | 21 Aug 2023 |
| Mattannur Project Sn 2 AE |
| Date: 05/01/2026 |
Work in progress | 77% Completed
Total quantity of pipe 42.5 km. 28 km distribution pipe laying completed.150 mm DI K9 Pumping main laying under progress. .250 HTC completed. Construction of 0.6LL SUMP cum pump house in progress at Kotheri . Pump house completed and finishing work is in progress. construction of 1.2LL OHSR at Velliyamparamba completed -Finishing work is in progress. Road restoration -15 roads completed.
| Mattannur Project Sn 2 AE |
| Date: 30/12/2025 |
Work in progress | 77% Completed
Total quantity of pipe 42.5 km. 28 km distribution pipe laying completed.150 mm DI K9 Pumping main laying under progress. .250 HTC completed. Construction of 0.6LL SUMP cum pump house in progress at Kotheri . Pump house completed and finishing work is in progress. construction of 1.2LL OHSR at Velliyamparamba completed -Finishing work is in progress. Road restoration -15 roads completed.