| Project | JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs -ZONE III |
|---|---|
| Project Code | KNRJJM022212626P3 |
| Type | Package |
| Main Project | JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Laying distribution system and providing FHTCs |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 144800000 |
| TS Number | 9796/2022-23 |
| Technical specification | 628 Nos FHTCs |
| Contractor | K.K.SURENDRAN (Mob: 9447038315) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 15/03/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 14 Dec 2023 |
| Expected date of Completion | 31/03/2025 |
| TS Date | 30 Dec 2022 |
|---|---|
| Estimate Approval | 30 Dec 2022 |
| NIT Approval | 30 Dec 2022 |
| Tender Closing | 28 Jan 2023 |
| Technichal Pre-Qualification | 30 Dec 2022 |
| Price bid opening | 30 Jan 2023 |
| Workorder Date | 15 Mar 2023 |
|---|---|
| NA | 23 Mar 2023 |
| Mattannur Project Sn 2 AE |
| Date: 05/01/2026 |
Work in progress | 68% Completed
46 km pipe laying completed. House connection and HTC work is also in progress. 172 Nos FHTC completed. 358 Nos HTC completed . construction of 0.70LL OHSR at panayathamparamb up to structure completed. 3LL OHSR at Panayathamparamb work in progress. up to 3rd brace beam completed. road restoration 10nos. irish concrete completed.
| Mattannur Project Sn 2 AE |
| Date: 30/12/2025 |
Work in progress | 67% Completed
46 km pipe laying completed. House connection and HTC work is also in progress. 169 Nos FHTC completed. 311 Nos HTC completed . construction of 0.70LL OHSR at panayathamparamb up to structure completed. 3LL OHSR at Panayathamparamb work in progress. up to 2nd brace beam completed.column upto 3rd brace beam completed. road restoration 10nos. irish concrete completed.