JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs -ZONE III

Project JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs -ZONE III
Project Code KNRJJM022212626P3
Type Package
Main Project JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Laying distribution system and providing FHTCs
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 144800000
TS Number 9796/2022-23
Technical specification 628 Nos FHTCs
Contractor K.K.SURENDRAN (Mob: 9447038315)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/03/2023
Scheduled date of Completion as per agreement 14 Dec 2023
Expected date of Completion 31/03/2025

Processing Dates

TS Date 30 Dec 2022
Estimate Approval 30 Dec 2022
NIT Approval 30 Dec 2022
Tender Closing 28 Jan 2023
Technichal Pre-Qualification 30 Dec 2022
Price bid opening 30 Jan 2023

Approval Dates

Workorder Date 15 Mar 2023
NA 23 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 05/01/2026

Work in progress | 68% Completed

46 km pipe laying completed. House connection and HTC work is also in progress. 172 Nos FHTC completed. 358 Nos HTC completed . construction of 0.70LL OHSR at panayathamparamb up to structure completed. 3LL OHSR at Panayathamparamb work in progress. up to 3rd brace beam completed. road restoration 10nos. irish concrete completed.

Mattannur Project Sn 2 AE
Date: 30/12/2025

Work in progress | 67% Completed

46 km pipe laying completed. House connection and HTC work is also in progress. 169 Nos FHTC completed. 311 Nos HTC completed . construction of 0.70LL OHSR at panayathamparamb up to structure completed. 3LL OHSR at Panayathamparamb work in progress. up to 2nd brace beam completed.column upto 3rd brace beam completed. road restoration 10nos. irish concrete completed.