Project | JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs -ZONE III |
---|---|
Project Code | KNRJJM022212626P3 |
Type | Package |
Main Project | JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Laying distribution system and providing FHTCs |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 144800000 |
TS Number | 9796/2022-23 |
Technical specification | 628 Nos FHTCs |
Contractor | K.K.SURENDRAN (Mob: 9447038315) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 15/03/2023 |
---|---|
Scheduled date of Completion as per agreement | 14 Dec 2023 |
Expected date of Completion | 31/03/2025 |
TS Date | 30 Dec 2022 |
---|---|
Estimate Approval | 30 Dec 2022 |
NIT Approval | 30 Dec 2022 |
Tender Closing | 28 Jan 2023 |
Technichal Pre-Qualification | 30 Dec 2022 |
Price bid opening | 30 Jan 2023 |
Workorder Date | 15 Mar 2023 |
---|---|
NA | 23 Mar 2023 |
Mattannur Project Sn 2 AE |
Date: 12/05/2025 |
Work in progress | 63% Completed
Earth Excavation and Pipe laying is in progress. Total distribution 48km,in that 46km pipe laying completed. House connection and HTC work is also in progress. 480nos HTC completed out of 628nos. construction of 0.70LL OHSR at panayathamparamb up to cover slab completed. 3LL OHSR at Panayathamparamb land NOC obtained from KINFRA on 26/11/24.but land owner not allowed to do the work.160mm PVC laying is at Panayathamparamb - Chlode Road completed. 90 mm 8 kg PVC laying completed at Kanad-Edayannur PWD road. Valve chamber work completed at panayathamparamba.
Mattannur Project Sn 2 AE |
Date: 03/05/2025 |
Work in progress | 63% Completed
Earth Excavation and Pipe laying is in progress. Total distribution 48km,in that 46km pipe laying completed. House connection and HTC work is also in progress. 480nos HTC completed out of 628nos. construction of 0.70LL OHSR at panayathamparamb up to cover slab completed. 3LL OHSR at Panayathamparamb land NOC obtained from KINFRA on 26/11/24.but land owner not allowed to do the work.160mm PVC laying is at Panayathamparamb - Chlode Road completed. 90 mm 8 kg PVC laying completed at Kanad-Edayannur PWD road. Valve chamber work completed at panayathamparamba.