Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Oct 2024 | earth excavation and pipe laying is in progress at keezhallur Zone1-92% work completed At keezhallur zone 2-Pipe laying in progress 15.50km completed out of 42km.Construction of sump 0.6LL capcity is in progress,overall 37% work completed At keezhallur Zone-3 Pipe laying in progress 36km pipe laid completed out of 48km.Construction 0.70LL OHSR up to plinth beam completed.over all 49% work completed | Mattannur Project Sn 2 AE | |
26 Jun 2023 | 46KM Pipe laid in zone-1 of keezhallur GP & HTC work is in progress.zone-2 work has tendered.zone-3 pipe laying is in progress | Mattannur Project Sn 2 AE |