JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs -ZONE I

Project JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs -ZONE I
Project Code KNRJJM022212626P1
Type Package
Main Project JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description 109 Km Distribution and 1500 Nos FHTCs
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 297800000
TS Number 638/2022-2023
Technical specification Laying distribution with 350 mm DI K9 to 90 mm PVC pipe of 109 Km and providing 1500 Nos FHTCs for Kothari area
Contractor Reena Engineers and Contractors Pvt.Ltd (Mob: 9447026559)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/11/2022
Scheduled date of Completion as per agreement 14 Aug 2023
Expected date of Completion 31/05/2025

Processing Dates

TS Date 31 Aug 2022
Estimate Approval 31 Aug 2022
NIT Approval 21 Oct 2022
Tender Closing 03 Oct 2022
Technichal Pre-Qualification 21 Oct 2022
Price bid opening 06 Oct 2022

Approval Dates

Workorder Date 15 Nov 2022
NA 29 Nov 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 12/05/2025

Work in progress | 94% Completed

Earth work Excavation and Pipe laying in progress. Total distribution 108.23 km, in that 104 km pipe laying completed. 1995 nos. HTC completed, in that 1787 nos. FHTC charged. Interconnections work in progress 35 nos. interconnection works completed. GI Fabrication work also finished. Road restoration of concrete roads of 35 nos. completed. LSGD road restoration work under progress.

Mattannur Project Sn 2 AE
Date: 03/05/2025

Work in progress | 94% Completed

Earth work Excavation and Pipe laying in progress. Total distribution 108.23 km, in that 104 km pipe laying completed. 1995 nos. HTC completed, in that 1787 nos. FHTC charged. Interconnections work in progress 35 nos. interconnection works completed. GI Fabrication work also finished. Road restoration of concrete roads of 35 nos. completed. LSGD road restoration work under progress.