Project | JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs -ZONE I |
---|---|
Project Code | KNRJJM022212626P1 |
Type | Package |
Main Project | JJM-KANNUR DISTRICT - KEEZHALLUR GRAMA PANCHAYATH-WSS TO KOLACHERY AND ADJOINING PANCHAYATHS -PHASE III-LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | 109 Km Distribution and 1500 Nos FHTCs |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 297800000 |
TS Number | 638/2022-2023 |
Technical specification | Laying distribution with 350 mm DI K9 to 90 mm PVC pipe of 109 Km and providing 1500 Nos FHTCs for Kothari area |
Contractor | Reena Engineers and Contractors Pvt.Ltd (Mob: 9447026559) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 15/11/2022 |
---|---|
Scheduled date of Completion as per agreement | 14 Aug 2023 |
Expected date of Completion | 31/05/2025 |
TS Date | 31 Aug 2022 |
---|---|
Estimate Approval | 31 Aug 2022 |
NIT Approval | 21 Oct 2022 |
Tender Closing | 03 Oct 2022 |
Technichal Pre-Qualification | 21 Oct 2022 |
Price bid opening | 06 Oct 2022 |
Workorder Date | 15 Nov 2022 |
---|---|
NA | 29 Nov 2022 |
Mattannur Project Sn 2 AE |
Date: 12/05/2025 |
Work in progress | 94% Completed
Earth work Excavation and Pipe laying in progress. Total distribution 108.23 km, in that 104 km pipe laying completed. 1995 nos. HTC completed, in that 1787 nos. FHTC charged. Interconnections work in progress 35 nos. interconnection works completed. GI Fabrication work also finished. Road restoration of concrete roads of 35 nos. completed. LSGD road restoration work under progress.
Mattannur Project Sn 2 AE |
Date: 03/05/2025 |
Work in progress | 94% Completed
Earth work Excavation and Pipe laying in progress. Total distribution 108.23 km, in that 104 km pipe laying completed. 1995 nos. HTC completed, in that 1787 nos. FHTC charged. Interconnections work in progress 35 nos. interconnection works completed. GI Fabrication work also finished. Road restoration of concrete roads of 35 nos. completed. LSGD road restoration work under progress.