Green Book-2017-18-Augmentation of RWSS to Aryad Panchayath-Construction of 3.5 LL capacity OHSr at komalapuram and Supplying and Laying of Clear water Pumping main and distribution lines and connected works in Aryad Panchayath

Project Green Book-2017-18-Augmentation of RWSS to Aryad Panchayath-Construction of 3.5 LL capacity OHSr at komalapuram and Supplying and Laying of Clear water Pumping main and distribution lines and connected works in Aryad Panchayath
Project Code ALPGOK0317486
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description The work Green Book-2017-18-Augmentation of RWSS to Aryad Panchayath-Construction of 3.5 LL capacity OHSr at komalapuram and Supplying and Laying of Clear water Pumping main and distribution lines and connected works in Aryad Panchayath comprises of construction of 3.50 LL OHSr at komalapuram Supplying and laying of distributino line 200 mm HDPE-2000m, 160 mm PVC 8 Kg-3000m, 110 mm PVC pipe 8 Kg-1000m, 90 mm PVC pipe 8 Kg-11000m and 200 mm DI K9 pipe 285m as clear water pumping main
Status Completed
District Alappuzha
Executing Office KIIFB Projects (ALP)
AS Amount (Rs) 49900000
AS Number GO(Rt.) 269/2017/WRD
TS Amount (Rs) 42400000
TS Number TS/2018-2019/2018/3366 Dated: 23-05-2018, TS/2018-2019/2018/3367 Dated: 23-05-2018
Total Bill Submitted (Rs) 30739295
Total Bill Paid (Rs) 7395207
Population Benefitted 42500
Capacity in MLD 62.00
Actual Project Completion Date 30 Sep 2021
Coverage Comprises of construction of 3.50 LL OHSR at Komalapuram Supplying and laying of distribution line 200 mm HDPE-2000m, 160 mm PVC 8 Kg-3000m, 110 mm PVC pipe 8 Kg-1000m, 90 mm PVC pipe 8 Kg-11000m and 200 mm DI K9 pipe 285m as clear water pumping main for Aryad Grama Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Green Book-2017-18-Augmentation of RWSS to Aryad Panchayath-Construction of 3.5 LL capacity OHSR at Komalapuram Alappuzha Project Dn
2 Green Book-Aryad-Supplying and laying of distributino line 200 mm HDPE-2000m, 160 mm PVC 8 Kg-3000m, 110 mm PVC pipe 8 Kg-1000m, 90 mm PVC pipe 8 Kg-11000m and 200 mm DI K9 pipe 285m as clear water pumping main Alappuzha Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Oct 2021 Work completed. Trial running in progress Alappuzha Project Dn PM
30 Sep 2021 Work Completed. Trail running is in progress Alappuzha Project Dn AE4
30 Sep 2021 work completed.Trail run in progress Alappuzha Project Dn AE4
29 Sep 2021 Interconnection works and valve fixing progressing Alappuzha Project Dn AE4
28 Sep 2021 Interconnection works and valve fixing progressing Alappuzha Project Dn AE4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 18/11/2018
Scheduled date of Completion of the Project 07 Nov 2019
Expected date of Completion 30/09/2021

Processing Dates

AS Date 29 Mar 2017
TS Date 23 May 2018