Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Oct 2021 | Work completed. Trial running in progress | Alappuzha Project Dn PM | |
30 Sep 2021 | Work Completed. Trail running is in progress | Alappuzha Project Dn AE4 | |
30 Sep 2021 | work completed.Trail run in progress | Alappuzha Project Dn AE4 | |
29 Sep 2021 | Interconnection works and valve fixing progressing | Alappuzha Project Dn AE4 | |
28 Sep 2021 | Interconnection works and valve fixing progressing | Alappuzha Project Dn AE4 | |
25 Sep 2021 | Construction of Valve chamber for distr. valve, Scour Overf low valve is also in progress | Alappuzha Project Dn AE4 | |
23 Sep 2021 | Painting of OHSR is progressing. Construction of Valve chamber for distr. valve, Scour Overf low valve is also in progress | Alappuzha Project Dn AE4 | |
22 Sep 2021 | Painting of OHSR is progressing. Construction of Valve chamber for distr. valve, Scour Overf low valve is started | Alappuzha Project Dn AE4 | |
20 Sep 2021 | Painting of OHSR is progressing | Alappuzha Project Dn AE4 | |
18 Sep 2021 | Painting of OHSR is progressing | Alappuzha Project Dn AE4 |