Work Plan Chart Revised
Project Plan
Agreement Slip and time extension
The agreement was executed on 06-09-2018 vide agt,. No. 10/2018-19/SE/PHC/ALP and the work commenced on 18-11-2018 for laying of pipe lines. The time extension was granted vide order no. KWA/PHC/ALP/DB-131/2016 dtd 07-12-2019 and extended upto 05-09-2020
Design Approval for OHSR
The design approval for 3.5 LL OHSR obtained on 27-05-2020. Then only the work for construction commenced.
TS slip
AS Document
The project has got AS vide GO (Rt)No. 269/2017/WRD dtd 30-03-2017 for Rs. 499.00 Lakhs